What’s next for Detroit’s glass crown?

For almost fifty years it has ruled the riverfront, and now it’s being rewritten. Under Bedrock and GM’s plan two towers would come down, apartments would join the hotel in the central tower, and the river would get a park and a marina. Follow every decision live right here, and we’ll show you where you can have your say.

LIVE updated 4 min ago · 120 stories tracked

People Mover from here 10:08 a.m. 10:13 a.m., 10:18 a.m.

Opened
1977the Detroit Plaza Hotel opened in March
Center tower
727 ft221.5 m, Michigan’s tallest building
Towers to go
2Towers 300 and 400, nearest the river
New homes
934205 of them affordable
Civic space
18 acresparks, plazas, waterfront, marina
All done
2036the plan’s last phase

01 / Live tracker

What’s happening with the RenCen right now?

Every fifteen minutes we check City Council agendas, the City’s Community Benefits page, DEGC documents, Bedrock’s project page and Detroit’s newsrooms. Anything new gets written up in our own words, always with the source. Around meetings we check even more often.

  1. PressThe Michigan Chronicle

    Detroit Council votes Tuesday on the $2.2 billion RenCen redevelopment package

    Detroit City Council is set to vote Tuesday, November 24, on the $2.2 billion RenCen and East Riverfront package, the last formal session before the year-end recess. It includes $548 million in tax breaks and incentives, among them a roughly two-decade state tax capture through a Transformational Brownfield plan, plus a $133 million community benefits package. Bedrock and GM wanted approval before Thanksgiving, while several council members say they need more time and answers; if it passes, demolition is expected to start next summer.

    Also reported by: ArabAmericanNews

  2. PressDetroit Free Press

    Detroit council votes Tuesday on $548M in incentives for the RenCen plan

    The Detroit City Council votes Tuesday, November 24, 2026, on about $548 million in tax breaks and incentives for Bedrock and GM's $2.2 billion RenCen and east riverfront redevelopment, plus the $133 million community benefits agreement. A vote planned for November 17 was postponed a week, and the Planning and Economic Development committee sent the package to the full council without a recommendation. It is the council's last formal session before its year-end recess; if approved, the Michigan Strategic Fund votes later.

    Also reported by: GM Authority, Wisevoter, Michigan Advance, CBS News, WXYZ Channel 7

  3. PressCars 108

    Detroit City Council votes 7-2 for the $2.2 billion RenCen redevelopment

    Detroit City Council voted 7-2 on Tuesday, November 24, at its last formal session of the year, to move ahead with Bedrock and GM's $2.2 billion RenCen and east riverfront plan. It removes the two towers closest to the river, the 300 and 400, which Bedrock says will be taken apart piece by piece, and adds about 5 acres of riverfront park. A motion by Denzel McCampbell to delay the vote until the new year failed; the Michigan Strategic Fund is expected to take it up in December.

  4. PressThe Michigan Chronicle

    7-2: Council approves $2.2 billion RenCen redevelopment

    Detroit City Council voted 7-2 on Tuesday, November 24, its last session of the year, for resolutions advancing the $2.2 billion RenCen and East Riverfront redevelopment. The plan puts $1.6 billion into the towers: the two empty 39-story towers would be taken apart, and the rest used for housing, offices and other uses. Bedrock CEO Jared Fleisher says the towers will come down piece by piece, set for next year, and Dan Gilbert is giving the new nonprofit $1 billion.

  5. PressFacebook

    City Council still has questions on the RenCen redevelopment

    Detroit City Council has remaining questions for the developers of the $2.2 billion RenCen redevelopment project, the Detroit Free Press reports.

    Also reported by: CTV News, ClickOnDetroit | WDIV Local 4

  6. PressConstruction Review

    City Council votes 7-2 for $2.2B RenCen and east riverfront redevelopment

    Detroit City Council voted 7-2 on Tuesday, November 24, 2026, at its last formal session of the year, to approve the Bedrock and GM plan. The vote covered about $473 million in tax incentives and $133.3 million in community benefits; the plan includes 900+ mixed-income homes and about 18 acres of parks and plazas. If the remaining approvals come through, Bedrock and GM aim to start selectively deconstructing two towers in the second half of 2027.

  7. PressFacebook

    City Council votes 7-2 to advance the $2.2 billion RenCen and east riverfront plan

    The Detroit City Council voted 7-2 on Tuesday, November 24, to pass resolutions advancing Bedrock and GM's $2.2 billion plan for the RenCen and the east riverfront. Council Members Gabriela Santiago-Romero and Denzel McCampbell voted no, saying the deal doesn't give Detroiters enough and moved too fast. State approval is the next big hurdle, and Bedrock and GM target the second half of 2027 to start deconstructing two of the five towers.

    Also reported by: Facebook, Instagram

  8. PressBridge Michigan

    City Council votes 7-2 for the $2.2 billion RenCen redevelopment

    The Detroit City Council voted 7-2 on Tuesday, November 24, at its final session of the year, to pass resolutions advancing the $2.2 billion RenCen and east riverfront redevelopment. It approved roughly $473-475 million in tax incentives and a $133 million community benefits package, and the plan demolishes two RenCen towers. Gabriela Santiago-Romero and Denzel McCampbell voted no; the work is planned in three phases, with completion projected for 2038.

  9. PressBridgeDetroit

    City Council votes 7-2 for the $2.2 billion RenCen redevelopment

    The Detroit City Council voted 7-2 on Tuesday, November 24, to advance the $2.2 billion Bedrock and GM plan for the RenCen and east riverfront; Denzel McCampbell and Gabriela Santiago-Romero voted no. Council approved about $475 million in tax breaks and incentives, plus a community benefits package worth $133 million over 30 years. The plan demolishes Towers 300 and 400 and the podium and adds housing and a riverfront park; the Michigan Strategic Fund and state brownfield approval come next.

    Also reported by: BridgeDetroit

  10. PressFacebook

    Detroit City Council votes 7-2 for the $2.2 billion RenCen redevelopment

    At its last session of the year on Tuesday, November 24, the Detroit City Council voted 7-2 for the resolutions moving ahead with the Bedrock and GM plan for the RenCen and the east riverfront. The package includes about $473 million in tax incentives and a $133.3 million community benefits package, and the plan removes two of the five towers. Construction cannot start yet: state approval is the next hurdle, and Bedrock and GM target the second half of 2027 to begin demolition.

  11. PressFOX 2 Detroit

    Detroit City Council approves the $2.2 billion RenCen plan

    Detroit City Council voted 7-2 on Tuesday, November 24, at its last formal session of the year at the Coleman A. Young Municipal Center, approving incentives and a community benefits agreement for the $2.2 billion RenCen and east riverfront redevelopment. The plan demolishes Towers 300 and 400 and the podium and adds housing, a riverfront park and an entertainment hub; Gabriela Santiago-Romero and Denzel McCampbell voted no. Bedrock and GM now seek state approvals from the Michigan Strategic Fund, with completion projected for 2038.

    Also reported by: Yahoo, FOX 2 Detroit

  12. PressYahoo

    Council votes 7-2 for $2.2B RenCen plan; Mayor Sheffield reacts

    Detroit City Council voted 7-2 on Tuesday, November 24, to move ahead with the $2.2 billion Renaissance Center and east riverfront redevelopment. The plan demolishes two towers and adds housing and a riverfront park, and council approved roughly $473–475 million in incentives against the $548 million Bedrock requested. Mayor Mary Sheffield said the vote moves Detroit one step closer to a new chapter for the riverfront.

    Also reported by: WXYZ Channel 7

  13. PressAxios

    Detroit City Council votes 7-2 for RenCen redevelopment incentives

    The Detroit City Council voted 7-2 on Tuesday, November 24, 2026, at its final session of the year, to approve resolutions advancing Bedrock and GM's $2.2 billion RenCen and east riverfront plan. It backs about $548 million in public subsidies and the demolition of Towers 300 and 400; Denzel McCampbell and Gabriela Santiago-Romero voted no. State approval is next, and the developers target the second half of 2027 to start deconstruction.

  14. PressMLive.com

    City Council votes 7-2 to advance the $2.2 billion RenCen redevelopment

    The Detroit City Council voted 7-2 on Tuesday, November 24, after hours of public comment, to pass resolutions moving ahead with Bedrock and GM's $2.2 billion RenCen plan. It calls for demolishing two of the five towers, with $1.6 billion for the original towers and $624 million for the east riverfront, phased over a decade. Gabriela Santiago-Romero and Denzel McCampbell voted no; supporters cited jobs and business, while organizer Theo Pride asked for a delay.

    Also reported by: MLive.com

  15. PressDeadline Detroit

    City Council votes 7-2 for the $2.2 billion RenCen redevelopment

    The Detroit City Council voted 7-2 on Tuesday, November 24, in its last formal session of the year, for the $2.2 billion Bedrock and GM plan for the RenCen and east riverfront. The resolutions cover the tax incentives and the community benefits agreement, and the plan demolishes Towers 300 and 400. Gabriela Santiago-Romero and Denzel McCampbell voted no; demolition is expected to start in summer 2027, but the Michigan Strategic Fund still has to consider the state tax breaks.

  16. PressCrain's Detroit

    Detroit City Council approves $2.2 billion RenCen plan: what happened at the vote?

    The Detroit City Council approved the $2.2 billion Bedrock-GM redevelopment plan on Tuesday, November 24, 2026, after hours of public comment. The plan covers more than 40 acres in and around the RenCen and the East Riverfront, seeks $548 million in incentives, and demolishes two of the RenCen's five towers, Towers 300 and 400. Developers say the mixed-use district will improve public access to the riverfront, and supporters say it will create thousands of jobs for Detroiters.

    Also reported by: Crain's Detroit

  17. PressThe Detroit News

    City Council hears public comment on the $2.2B RenCen deal

    Detroit City Council held public comment on Tuesday, November 24, 2026, its final meeting of the year, on the $2.2 billion Bedrock and GM RenCen plan. It cuts the complex from five towers to three by demolishing towers 300 and 400 and adds a riverfront park and public space. The council was expected to vote on a $133 million community benefits agreement and a brownfield agreement after postponing the November 17 vote. Bedrock and GM seek about $548 million in public subsidies, and opponents want more time and review.

  18. PressYahoo

    Detroit council votes 7-2 for the $2.2B RenCen redevelopment

    The Detroit City Council voted 7-2 on Tuesday afternoon, November 24, 2026, to move ahead with the $2.2 billion Bedrock and GM plan for the RenCen and the east riverfront. The package includes tax incentives, a $133.3 million community benefits agreement and a brownfield agreement; two of the five towers come down, and the plan adds 900+ mixed-income homes and about 18 acres of parks and plazas. Gabriela Santiago-Romero and Denzel McCampbell voted no, and the council now goes into winter recess.

  19. PressThe Detroit News

    Will City Council vote on the $2.2 billion RenCen plan?

    Detroit City Council postponed its vote on the Bedrock and GM RenCen plan on Tuesday, November 17, in the evening. The $2.2 billion plan includes tearing down towers 300 and 400. Herb Strather and others asked for a 90-day delay to study alternatives such as educational space, and Councilman Coleman Young II says he will vote yes. A vote is expected Tuesday, November 24.

  20. PressClickOnDetroit | WDIV Local 4

    Detroit City Council revisits RenCen vote, its last chance this year

    The Detroit City Council takes up the $2.2 billion RenCen and East Riverfront redevelopment package again on Tuesday, November 24, 2026, after postponing the vote by one week on November 17. The package includes about $548 million in tax breaks and incentives plus a community benefits agreement, and council members said they still needed answers to several questions. It is the full council's last formal session before the year-end recess.

    Also reported by: WDIV Local 4

  21. PressCBS News

    Detroit City Council votes on the $2.2 billion RenCen redevelopment

    The Detroit City Council votes on the $2.2 billion Renaissance Center and East Riverfront redevelopment at its meeting on Tuesday, November 24, at 10 a.m. The package has about $548 million in tax breaks and incentives, a community benefits agreement and related resolutions; the plan would demolish Towers 300 and 400 and add about 18 acres of public civic space. Council postponed the vote one week on November 17 and aims to decide before the Thanksgiving recess.

  22. PressClickOnDetroit | WDIV Local 4

    Detroit City Council to vote Tuesday on the RenCen plan?

    The Detroit City Council is expected to vote at 10 a.m. on Tuesday, November 24, 2026, at its last formal session of the year, on the $2.2 billion Bedrock and GM plan for the RenCen and east riverfront. The package includes tax breaks, incentives and a Community Benefits Agreement, demolishes two towers and adds about 18 acres of public space. The council postponed the vote on November 17 by one week because members still had questions.

  23. PressFOX One

    Detroit City Council votes 7-2 for the $2.2 billion RenCen redevelopment

    The Detroit City Council voted 7-2 on Tuesday, November 24, at about 3 p.m., to pass resolutions advancing the $2.2 billion redevelopment of the RenCen and the east riverfront. The plan demolishes two of the five towers, renovates the rest and adds housing, a riverfront park, restaurants and shops; the developers requested $548 million in tax breaks and incentives, and the package includes a $133 million community benefits plan. Denzel McCampbell and Gabriela Santiago-Romero voted no, and the three-phase project is projected to finish in 2038.

  24. PressFOX 2 Detroit

    Wayne County Commission backs RenCen plan unanimously; Detroit City Council is next

    The Wayne County Commission unanimously passed a resolution on Monday, November 23, supporting GM and Bedrock's $2.2 billion redevelopment of the Renaissance Center and the riverfront. The resolution only shows support and does not grant the needed approvals. The Detroit City Council meets next on Tuesday, November 24, its last session before the year-end recess, and Bedrock and GM want approval before Thanksgiving.

    Also reported by: FOX 2 Detroit

Earlier stories (96)
  1. PressFOX 2 Detroit

    Detroit Council votes Tuesday on $548M in RenCen tax breaks

    Detroit City Council is expected to vote Tuesday, November 24, on about $548 million in tax breaks and incentives for the RenCen redevelopment, plus a community benefits agreement. Council postponed the votes by one week on November 17. Bedrock and GM want approval before Thanksgiving so the Michigan Strategic Fund can consider a state tax break before the governor changes. The $2.2 billion plan would demolish two of the five towers.

    Also reported by: Yahoo, FOX 2 Detroit

  2. PressFacebook

    City Council still has questions for developers of the $2.2 billion RenCen plan

    Detroit City Council has more questions for Bedrock and GM about their $2.2 billion redevelopment of the Renaissance Center and the East Riverfront. The developers are asking for about $548 million in subsidies and offer a $133 million community benefits package. The council's Planning and Economic Development Committee voted 3-2 to send the community benefits agreement to the full council without a recommendation, and the full council delayed its vote.

  3. PressCrain's Detroit

    RenCen vote delayed: Detroit council pushes it back a week

    Detroit City Council postponed its vote on tax incentives and the community benefits agreement for the RenCen and east riverfront on Tuesday, November 17, after members said they needed more time to review it. Many residents say the roughly $548 million subsidy is too high, the process is rushed, and ownership and public access are unresolved. Bedrock and GM want approval before the December recess; the vote moves to the council's meeting around Tuesday, November 24.

  4. PressFacebook

    Why is Bedrock pushing for RenCen approval before council's December recess?

    Bedrock and GM propose a $2.2 billion RenCen redevelopment, and Detroit City Council postponed its vote by one week on Tuesday, November 17. The companies want all local approvals before the December recess because they worry incoming Gov. Jocelyn Benson could change how big development incentives get approved in 2027. Residents and advocacy groups urged council to slow down over the nearly $500 million in public funding and incentives, the ownership structure and public access.

  5. PressCity Bureau Documenters

    Wayne County Commission backs the RenCen redevelopment with a resolution

    The Wayne County Commission approved a resolution supporting the Renaissance Center redevelopment at its meeting on Thursday, November 19, 2026. It also approved a $700,000 grant for a 3-year body camera program for sheriffs and rejected an agreement with Metrotech Automotive over a dispute about the company's use of the county logo.

  6. PressWisevoter

    City Council delays vote on $548 million in RenCen subsidies

    The Detroit City Council postponed its vote on public incentives and the community benefits agreement for the $2.2 billion RenCen and east riverfront redevelopment at its Tuesday, November 17, session. Bedrock and GM are asking for about $548 million, including more than $473 million in tax breaks over 30 years, to demolish two RenCen towers and build housing and a riverfront park. Council members said they needed more time to review the request; the vote moves to the council's last formal session of the year, and more than 130 people had signed up to speak on November 17.

  7. PressDetroit Free Press

    Bedrock fears delays under the next governor: what happens to the RenCen vote?

    Bedrock and GM want Detroit City Council to approve the RenCen incentives before its December recess, because they fear the approval process could slow down once Jocelyn Benson takes office in 2027. On Tuesday, November 17, the council postponed its vote on the incentives and the community benefits agreement by one week. If the council approves, the package goes to the Michigan Strategic Fund.

    Also reported by: Belleville News-Democrat

  8. PressMjengo Hub

    Detroit City Council postpones its RenCen redevelopment vote

    Detroit City Council on Tuesday, November 17, 2026, postponed its vote on public incentives and a community benefits agreement for the $2.2 billion RenCen and east riverfront redevelopment, saying members needed more time to review it. The plan would demolish two of the five towers and add housing, entertainment, retail and a riverfront park. Developers want local approvals before Thanksgiving, and the vote moves to the council's next session.

  9. PressMIRS.news

    Port Authority chief talks RenCen, water shuttles and tariffs

    The Port Authority's executive director discussed the RenCen, water shuttles and tariffs in an interview, MIRS.news reports.

  10. PressThe Michigan Chronicle

    Bedrock CEO Jared Fleisher talks RenCen redevelopment and Detroit's future

    Bedrock CEO Jared Fleisher discussed Detroit's future and the RenCen redevelopment, The Michigan Chronicle reports.

    Also reported by: The Michigan Chronicle

  11. PressCity Bureau Documenters

    Detroit City Council pushes RenCen vote back one week

    Detroit City Council, led by President James Tate, postponed its vote on the main parts of the $2.2 billion RenCen and east riverfront plan at the start of its formal session on Tuesday, November 17. The vote covers the public incentives and the community benefits agreement. Tate said key questions are unanswered, and the council wants another week to review. Public comment ran over 2 hours, both for and against the plan.

  12. PressThe Detroit News

    Detroit City Council postpones its RenCen vote

    The Detroit City Council postponed its RenCen vote, which could have happened Tuesday, November 17. The items before council are a tax-incentive package and the $133 million community benefits agreement, which the Planning and Economic Development Committee sent to the full council without a recommendation on Thursday, November 12, by a 3-2 vote. Bedrock and GM want all local approvals before council's winter recess.

    Also reported by: ClickOnDetroit | WDIV Local 4, WXYZ Channel 7, Yahoo, Yahoo News Canada, Audacy

  13. PressOutlier Media

    RenCen vote postponed: Detroit City Council pushes it back one week

    Detroit City Council President James Tate announced at the start of the formal session on Tuesday, November 17, that the vote on the RenCen tax incentives and community benefits agreement is postponed by one week. Key questions remain unanswered, including why the DEGC signed a nondisclosure agreement with Bedrock. The council's last formal session of the year is Tuesday, November 24, and the vote is expected then.

  14. PressBridgeDetroit

    Detroit City Council delays RenCen package vote by one week

    Detroit's City Council postponed its vote on the $2.2 billion RenCen and East Riverfront package on Tuesday, November 17, at the start of the meeting. Council President James Tate said key questions remain unanswered, and members and residents are pressing Bedrock and GM for more job guarantees and public ownership of land next to the towers. Council could vote at its last formal session of the year on Tuesday, November 24.

  15. PressBridgeDetroit

    City Council delays RenCen vote by one week

    Detroit City Council on Tuesday, November 17, postponed its votes on the tax incentives and the community benefits agreement for the RenCen and east riverfront redevelopment, with President James Tate pointing to unanswered questions. Bedrock declined to comment. The vote is expected at Council's last session of the year on Tuesday, November 24.

  16. PressAxios

    Detroit City Council delays RenCen vote by one week

    Council President James Tate postponed the council's vote on tax incentives and a community benefits agreement for Bedrock and GM's $2.2 billion RenCen plan on Tuesday, November 17. Tate said a number of questions remain open, and members want more time to review the subsidy request. The vote is now set for Tuesday, November 24, the council's last formal session before its year-end recess.

  17. PressYour sayMichigan Public

    Detroit council pushes RenCen tax incentive vote back one week

    Detroit City Council postponed its vote on the tax incentives and community benefits agreement for the $2.2 billion RenCen and east riverfront project on Tuesday, November 17. Council President James Tate cited open questions, and members say they need more time to review the roughly $548 million subsidy request. The vote is now set for Tuesday, November 24, the council's last formal session before recess; you can weigh in through public comment or by contacting council members.

  18. PressCrain's Detroit

    Detroit council postpones its RenCen votes

    At the start of its Tuesday, November 17 meeting, the Detroit City Council postponed its votes on the RenCen incentives and the community benefits agreement. Council President James Tate said questions remain unanswered and gave no new date. Bedrock and GM want all local approvals before the winter recess, while critics call the process rushed.

  19. PressDetroit Free Press

    Detroit City Council postpones its RenCen vote

    Council President James Tate announced at the start of the Tuesday, November 17 meeting that the full council vote on the RenCen community benefits agreement and tax incentives is postponed. Tate said questions haven't been answered, and Gabriela Santiago-Romero wanted more time to review, while the developers wanted approval by Thanksgiving. No new vote date has been given.

    Also reported by: Yahoo, Detroit Free Press

  20. PressYour sayClickOnDetroit | WDIV Local 4

    RenCen: committee sends plan to full council as public opinion splits

    The City Council's Planning and Economic Development Committee voted 2-1 on Thursday, November 12, to send the RenCen redevelopment package to the full council; Latisha Johnson and Coleman A. Young II voted yes, Gabriela Santiago-Romero no. The package covers a $2.2 billion project with $548 million in public subsidies and the $133 million Community Benefits Agreement. The full council could vote as soon as Tuesday, November 17, and residents can contact council members or speak during public comment at council sessions.

  21. PressYour sayClickOnDetroit | WDIV Local 4

    City Council delays RenCen vote by one week

    Detroit City Council on Tuesday, November 17, postponed its vote on the tax incentives and community benefits agreement for the $2.2 billion RenCen and east riverfront plan, with Council President James Tate citing unanswered questions. The council's last formal session of the year is Tuesday, November 24, and the vote is expected then; you can comment in person or on Zoom.

  22. PressYour sayOutlier Media

    RenCen vote at City Council: $548 million in public subsidies on the table

    Detroit City Council could vote at its formal session on Tuesday, November 17, on tax incentives and a $133 million Community Benefits Agreement for the $2.2 billion RenCen and East Riverfront plan. The Planning and Economic Development Committee sent the items on without a recommendation on Thursday, November 12; the project needs $548 million in public subsidies and demolishes two of five towers. Council wants approval before Thanksgiving, and you can contact council members or speak during public comment at council sessions.

  23. PressOutlier Media

    RenCen deal: what should council ask before it votes?

    Detroit City Council's Planning and Economic Development Committee voted 2-1 on Thursday, November 12, to send Bedrock and GM's $2.2 billion RenCen and east riverfront plan to the full council. The council would vote on the tax incentives and the community benefits agreement, possibly as soon as Tuesday, November 17. The developers want approval before the council's recess, while key financial questions remain open on about $548 million in subsidies over 30 years.

    Also reported by: Outlier Media

  24. PressBridgeDetroit

    NAC members: no reason to delay the RenCen community benefits agreement

    Several members of the Neighborhood Advisory Council (NAC) say they stand by the agreement they negotiated with Bedrock and GM and "see no reason to delay" the project. They say the city's role is to evaluate and approve the project so the state can invest in the RenCen. The full City Council vote has no date yet; on Thursday, November 12, the council's Planning and Economic Development Committee voted 3-2 to send the agreement forward without a recommendation.

    Also reported by: BridgeDetroit

  25. PressYour sayBridgeDetroit

    RenCen plan moves on; community meeting Monday evening

    The City Council's Planning and Economic Development Committee voted 2-1 on Thursday, November 12, 2026, after more than six hours, to send the RenCen plan to the full council: the tax incentives and the $133 million Community Benefits Agreement. Latisha Johnson and Coleman A. Young II voted yes, Gabriela Santiago-Romero no. The full council could vote as soon as Tuesday, November 17, 2026. Council Member Mary Waters hosts a community meeting Monday, November 16, 5-7 p.m. at the Coleman A. Young Community Center, and you can join online with registration.

    Also reported by: BridgeDetroit

  26. PressBridgeDetroit

    RenCen: 3-2 in committee, full council could vote as soon as Tuesday

    The City Council's Planning and Economic Development Committee voted 3-2 on Thursday, November 12, to send the RenCen package, with its tax breaks, incentives and community benefits agreement, to the full council without a recommendation. Residents and Save the RenCen want a delay because they say requested items are missing, while chair Latisha Johnson said it was time for the full council to examine the plan. The full council could vote as soon as Tuesday, November 17.

  27. PressBridgeDetroit

    RenCen deal heads to full council: a vote could come as soon as Tuesday

    Detroit City Council's Planning and Economic Development Committee voted 3-2 on Thursday, November 12, to send the RenCen community benefits agreement to the full council without a recommendation. Bedrock and GM say the project can't happen without the $548 million in public subsidies, while residents and advocates asked for a delay. The full council could vote as soon as Tuesday, November 17, and wants approval before the Thanksgiving recess.

  28. PressBridgeDetroit

    Why does the NAC's lone "no" vote want the council to delay the RenCen deal vote?

    TeRon Haynes Jr., an elected Neighborhood Advisory Council (NAC) member and its only "no" vote on the community benefits agreement, asks the City Council in a BridgeDetroit guest commentary to delay its vote. He says the marina, theater and observation deck are only verbal, nonbinding promises, the 10-year timeline isn't contractual, and nothing goes to public transit. The full council could take it up as soon as Tuesday, November 17, and the developers want approval by Thanksgiving.

    Also reported by: BridgeDetroit

  29. PressThe Detroit News

    Gilbert's PAC gave cash to council members as the RenCen vote nears

    Dan Gilbert's political action committee (PAC) has given cash gifts to Detroit City Council members while the council prepares to vote on the $2.2 billion RenCen plan. On Thursday, November 12, the council's Planning and Economic Development Committee sent the community benefits agreement to the full council without a recommendation. Council members aim to approve the plan before Thanksgiving, when the council goes on recess until next year.

    Also reported by: Belleville News-Democrat

  30. PressYour sayMichigan Public

    RenCen: committee sends $548M subsidy package to full council as protesters demand a delay

    The Detroit City Council's Planning and Economic Development Committee sent the community benefits agreement and tax breaks for the $2.2 billion RenCen project to the full council without a recommendation on Thursday, November 12. Protesters outside the Coleman A. Young Municipal Center rallied against the roughly $548 million in subsidies and called the public input period too short. The full council could take it up as soon as Tuesday, November 17, and residents can comment in person or virtually through the City Clerk's agenda page.

  31. PressDeadline Detroit

    RenCen: committee sends community benefits deal to full council with no recommendation

    The Detroit City Council's Planning and Economic Development Committee voted 3-2 on Thursday, November 12, to send the community benefits agreement to the full council without a recommendation. The $43.5 million package is tied to the $2.2 billion RenCen and East Riverfront plan. Residents at the Coleman A. Young Municipal Center asked for a delay so there is more time for input. Nicole Small of Save the RenCen said items residents requested over 10 weeks "disappeared out of the CBA." Council members aim to vote before Thanksgiving.

  32. PressMichigan Advance

    Committee sends RenCen community benefits deal to full council with no recommendation

    Detroit City Council's Planning and Economic Development Committee voted 3-2 on Thursday, November 12, to send the $43.5 million community benefits agreement tied to the $2.2 billion RenCen and East Riverfront plan to the full council without a recommendation. Residents asked for a delay, and Councilmember Gabriela Santiago-Romero opposed the move because she wanted more time to review it. The full council vote has no date yet.

  33. PressSanta Clara University

    Dan Gilbert's PAC cash gifts to Detroit council members surface as RenCen vote nears

    Cash gifts from Dan Gilbert's political action committee (PAC) to Detroit City Council members have come to light as the RenCen vote approaches. Davina Hurt, director of government ethics, spoke about the issue to The Detroit News.

  34. PressThe Detroit News

    Council committee splits 2-1, sends $2.2B RenCen package to full council without a recommendation

    Detroit City Council's Planning and Economic Development Committee voted 2-1 on Thursday, November 12, 2026, to send the $2.2 billion RenCen redevelopment package of tax breaks, incentives and community benefits to the full council with no recommendation. Latisha Johnson and Coleman Young II voted yes, Gabriela Santiago-Romero voted no, and Johnson still has questions about the nonprofit ownership model. The full council could vote as soon as Tuesday, November 17.

  35. PressDetroit Free Press

    Committee sends $2.2B RenCen plan to full council with no recommendation

    The Detroit City Council's Planning and Economic Development Committee voted 2-1 on Thursday, November 12, to send the Bedrock and GM $2.2 billion RenCen plan to the full council without a recommendation. Chair Latisha Johnson and Coleman Young II voted yes; Gabriela Santiago-Romero voted no, saying the process has been rushed. The full council could vote as soon as Tuesday, November 17.

  36. PressCrain's Detroit

    RenCen: council committee takes up the $2.2 billion plan

    Detroit City Council's Planning and Economic Development Committee had the $2.2 billion RenCen and east riverfront plan on its agenda Thursday, November 12, including the community benefits report, the benefits provisions, a public hearing and a commercial rehabilitation district, which is a tax abatement. Bedrock and GM say the project can't happen without about $548 million in tax breaks and incentives; the full council votes after the committee, and the developers want to start next summer.

  37. PressCBS News

    Group asks Council to delay vote on RenCen plan

    A group is calling on the Detroit City Council to delay its vote on the proposed Renaissance Center redevelopment plan and to share more details about it.

  38. PressFOX 2 Detroit

    Detroiters voice concerns about the RenCen plan at council committee

    The City Council's Planning and Economic Development Committee met Thursday, November 12, 2026, at 10 a.m. on the 13th floor of the Coleman A. Young Municipal Center to take up the RenCen and riverfront redevelopment. Many residents urged council members to take their time and asked that the Law Department's confidential memo on revenue sharing and community ownership be made public. The full council is expected to vote on the $2.2 billion plan before the Thanksgiving recess.

    Also reported by: FOX 2 Detroit

  39. PressCrain's Detroit

    Bill Emerson leaves Rocket's board for the new RenCen nonprofit

    Bill Emerson, a three-decade Rocket Companies executive, resigned from Rocket's board effective immediately on Friday, November 6, 2026, to focus on the new nonprofit that would own and redevelop the RenCen. Rocket says the move is unrelated to any disagreement over its operations. On Tuesday, November 10, the board named Adam Blitzer to replace him, effective November 16.

  40. PressYour sayDetroit Free Press

    Jamaine Dickens: the RenCen deal costs Detroiters nothing

    Jamaine Dickens, chair of the Neighborhood Advisory Council for the RenCen and east riverfront project, defends the community benefits package in a Free Press column: he says it is worth more than $130 million, including $43 million in direct benefits, and that none of the funding comes from city property taxes. A City Council committee holds a public hearing Thursday, November 12, at 10 a.m. at the Young Municipal Center or virtually, and plans to vote on whether to recommend the $548 million in incentives and the benefits package.

  41. PressYour sayBridgeDetroit

    RenCen benefits hearing Thursday: how to weigh in

    Detroit City Council's Planning and Economic Development committee meets Thursday, November 12, at 10 a.m. on the 13th floor of the Coleman A. Young Municipal Center to review the community benefits agreement for the $2.2 billion RenCen redevelopment, with a public hearing and a commercial rehabilitation district tax abatement request on the agenda. You can comment in person or virtually through the City Clerk's council agendas page; no vote has been reported yet.

    Also reported by: BridgeDetroit

  42. PressYour sayCity of Detroit

    Mary Waters hosts a Renaissance Center community meeting on November 16

    City Council Member At-Large Mary Waters is holding a community meeting on the Renaissance Center on Monday, November 16, from 5 to 7 p.m. at the Coleman A. Young Recreation Center, 2751 Robert Bradby Drive. You can attend in person or on Zoom, but registration is required.

  43. PressCity Bureau Documenters

    City Council moves RenCen reports and requests to new business

    The Detroit City Council moved several reports and information requests about the Renaissance Center development to new business at its formal session. Residents also voiced frustration with city services, especially housing, and a few spoke against the solar neighborhoods initiative.

  44. PressREJournals

    $43.5 million community benefits deal backed for RenCen redevelopment

    The Neighborhood Advisory Council (NAC) backed a $43.5 million community benefits agreement for the $2.2 billion RenCen redevelopment, signed with Bedrock and GM on Thursday, November 5. It sets aside $15 million for housing, $10 million for small businesses, $8 million for a community hub, $6 million for workforce development and education, and $4.5 million for parking. Officials called it the largest such agreement in Detroit's history.

  45. PressWXYZ Channel 7

    Eight of nine NAC members sign letter backing the RenCen community benefits agreement

    Eight of the nine members of the Neighborhood Advisory Council (NAC) signed a letter supporting the community benefits agreement for the $2.2 billion RenCen redevelopment on Thursday, November 5. The agreement's direct spending totals $43.5 million, including $15 million for housing, $10 million for small businesses and $8 million for the community hub. A City Council committee plans to vote on recommending the package on November 12, and then the full Council decides.

    Also reported by: WXYZ Channel 7

  46. PressCBS News

    RenCen: NAC backs $43.5M community benefits deal, City Council vote still ahead

    Eight of nine members of the RenCen project's Neighborhood Advisory Council signed a $43.5 million community benefits agreement with Bedrock and GM: $15 million for housing, $10 million for small businesses, $8 million for a community hub, $6 million for workforce development and education, and $4.5 million for parking. The developers also committed to $90 million in payments in lieu of taxes over 30 years. City Council still has to approve it, and the city aims to finish before Thanksgiving.

    Also reported by: CBS News

  47. PressMLive.com

    NAC votes 8-1 for $133.3M RenCen community benefits package

    The Neighborhood Advisory Council (NAC) voted 8-1 on Tuesday, October 27, in the evening to recommend a $133.3 million community benefits package for the $2.2 billion RenCen redevelopment. It includes $43.5 million in direct developer spending and nearly $90 million in PILOT payments to the city, and 20% of the 934 planned housing units would be affordable. Teron Haynes Jr. cast the only no vote because the city gets no ownership or revenue sharing; the council's Planning and Economic Development Committee votes November 12, then the full council.

  48. PressCrain's Detroit

    Andiamo and Joe Muer will stay in the RenCen into 2027

    Joe Vicari Restaurant Group's two restaurants, Andiamo Detroit Riverfront and Joe Muer Seafood, will stay open into 2027 in the nearly empty Renaissance Center. The group is also opening a new Joe Muer Seafood + Chops in January as the flagship restaurant of the JW Marriott Detroit Water Square next door, timed with the hotel's January 2027 debut.

  49. PressNewser

    Dan Gilbert pledges $1 billion toward redeveloping the RenCen

    Dan Gilbert, the Rocket Mortgage co-founder, pledged $1 billion to redevelop the Renaissance Center through a new nonprofit he is creating, structured as a 501(c)(4). Total project cost could reach $2.2 billion with GM's investment. The Downtown Development Authority has put in $75 million, to be reimbursed, and the project is seeking more than $300 million in other tax benefits.

  50. PressCrain's Detroit

    The RenCen's reckoning: nearly 50 years in the making

    Dan Gilbert's Bedrock and GM are working on redeveloping the RenCen and the GM-owned parking lots to its east, a $2.24 billion project. Bedrock and GM officials put the public incentive price tag at $547.93 million. Crain's Kirk Pinho writes the RenCen has been a failure for nearly 50 years and that Gilbert is inching closer to a long-coveted riverfront development.

  51. PressDetroit Regional Chamber

    Chamber urges City Council to back RenCen community benefits deal

    The Detroit Regional Chamber is calling on City Council to approve the community benefits agreement and financing tools for the $2.24 billion RenCen and east riverfront project. The Neighborhood Advisory Council (NAC) voted 8-1 on Tuesday, October 27, in the evening to recommend the agreement. It goes to the council's Planning and Economic Development Committee on November 12, with a final full-council vote later.

  52. PressDetroit Free Press

    NAC backs $133.3M RenCen community benefits package, 8-1

    The Neighborhood Advisory Council (NAC) voted 8-1 on Tuesday, October 27, in the evening to recommend a $133.3 million community benefits package for the $2.2 billion RenCen redevelopment. It includes $43.5 million in direct developer spending and nearly $90 million in voluntary payments in lieu of taxes to the city; this is not final approval. The package goes to the City Council's Planning and Economic Development Committee on November 12, and the full council votes later.

  53. PressBelleville News-Democrat

    Council committee votes Nov. 12 on $548 million RenCen incentives

    At its meeting and public hearing on Thursday, October 29, the Detroit City Council's Planning and Economic Development Committee announced it will vote Thursday, November 12, on whether to recommend the $548 million incentives request and the $133 million Community Benefits package. The full council votes after that, with no date set yet. Bedrock and GM want all local approvals before the council's December recess.

  54. PressCity Bureau Documenters

    NAC votes 8-1 to back RenCen community benefits package

    The Neighborhood Advisory Council (NAC) voted 8-1 on Tuesday evening, October 27, to recommend the community benefits agreement negotiated with Bedrock and General Motors for the $2.2 billion RenCen redevelopment. Teron Haynes Jr. cast the only no vote, citing the lack of direct public ownership or revenue sharing with the city. The vote is only a recommendation; Detroit City Council makes the final decision.

    Also reported by: City Bureau Documenters

  55. PressCrain's Detroit

    What's in the $43.3M RenCen community benefits package?

    Detroit's Neighborhood Advisory Council voted 8-1 on Tuesday, October 27, in the evening to recommend a community benefits package for the $2.2 billion Renaissance Center redevelopment. Direct benefits come to $43.3 million, including $10 million for affordable housing across the city and $5 million for the Affordable Housing Trust Fund, and 20% of the 934 planned units will be affordable. Bedrock said it intends to bring back a movie theater, and the package goes to City Council for final approval in November.

  56. PressDetroit Free Press

    NAC backs the largest-ever RenCen community benefits package, 8-1

    The Neighborhood Advisory Council voted 8-1 on Tuesday evening, October 27, to recommend the RenCen redevelopment's community benefits package, described as the largest in city history. Teron Haynes Jr. cast the lone no vote, citing no direct public ownership and no revenue sharing with the city. Bedrock and GM are seeking $548 million in incentives, and the package goes to City Council for final approval in November.

    Also reported by: BridgeDetroit

  57. PressFacebook

    NAC votes 8-1 to back RenCen Community Benefits package

    The Neighborhood Advisory Council voted 8-1 on Tuesday evening, October 27, to recommend that City Council approve the Community Benefits package for the $2.2 billion RenCen redevelopment. The $133.3 million package has $43.5 million in direct developer spending and nearly $90 million in PILOT payments to the city. Teron Haynes Jr. voted no, citing the lack of public ownership and revenue sharing. The agreement goes to the council's Planning and Economic Development Committee on November 12.

  58. PressCTV News

    Neighborhood council backs RenCen community benefits deal 8-1

    The Neighborhood Advisory Council (NAC) voted 8-1 on Tuesday, October 27, in the evening to recommend the Community Benefits Agreement for the $2.2 billion RenCen redevelopment. The package has $43.5 million in direct developer spending plus nearly $90 million in voluntary PILOT payments to the city, $133.3 million in all. The vote is only a recommendation: City Council's Planning and Economic Development Committee takes it up November 12, with a full council vote later. Teron Haynes Jr. cast the no vote, objecting to the lack of public ownership or revenue sharing.

    Also reported by: CTV News

  59. PressAxios

    Neighborhood Advisory Council backs RenCen community benefits package 8–1

    The Neighborhood Advisory Council (NAC) voted 8–1 on the evening of Tuesday, October 27, to recommend a $133.3 million community benefits package for the $2.2 billion RenCen redevelopment. It includes $43.5 million in direct developer spending and nearly $90 million in PILOT payments to the city, and 20% of the 934 planned housing units would be affordable. Teron Haynes Jr. cast the no vote, citing no direct public ownership and no revenue-sharing with the city. The agreement goes to City Council's Planning and Economic Development Committee on Thursday, November 12.

  60. PressFacebook

    Community Benefits package for $2.2 billion RenCen project gets preliminary approval

    The Community Benefits package for the $2.2 billion Renaissance Center redevelopment received preliminary approval on October 27. It was billed as the largest in Detroit's history. Bedrock executive Jake Chidester spoke at the meeting.

  61. PressThe Michigan Chronicle

    NAC votes 8–1 to back $133.3M community benefits package for the RenCen

    Detroit's Neighborhood Advisory Council (NAC) voted 8–1 on Tuesday, October 27, in the evening to recommend the Community Benefits Agreement for the RenCen redevelopment. The package has $43.5M in direct developer spending and nearly $90M in voluntary payments in lieu of taxes to the city, $133.3M in all. Teron Haynes Jr. cast the only no vote, citing no public ownership and no revenue sharing; the agreement goes to the City Council's Planning and Economic Development Committee on November 12.

  62. PressThe Detroit News

    NAC backs RenCen community benefits package 8-1

    The Neighborhood Advisory Council (NAC) voted 8-1 on Tuesday evening, October 27, to recommend that City Council approve the Community Benefits Agreement for the $2.2 billion RenCen redevelopment. The $133.3 million package includes $43.5 million in direct developer spending, nearly $90 million in PILOT payments to the city and $10 million for affordable housing. Teron Haynes Jr. cast the only no vote, citing no public ownership and no revenue-sharing; the agreement goes to Council's Planning and Economic Development Committee on Thursday, November 12.

    Also reported by: Belleville News-Democrat

  63. PressThe Detroit News

    Renaissance Center NAC backs community benefits package 8-1

    The Neighborhood Advisory Council (NAC) voted 8-1 on Tuesday evening, October 27, to recommend the community benefits package for the $2.2 billion RenCen redevelopment, valued at $133.3 million: $43.5 million in direct developer spending plus nearly $90 million in PILOT payments to the city. Teron Haynes Jr. voted no because the deal has no direct public ownership and no revenue-sharing with the city. The agreement goes to City Council's Planning and Economic Development Committee on November 12, and the full council votes later.

  64. PressCrain's Detroit

    8-1: NAC backs RenCen community benefits package

    Detroit's Neighborhood Advisory Council voted 8-1 on Tuesday, October 27, in the evening to recommend a $133.3 million community benefits package for the $2.2 billion RenCen redevelopment. It includes $43.5 million in direct developer spending and nearly $90 million in PILOT payments to the city. The City Council's Planning and Economic Development Committee takes it up November 12, and the full council votes later.

  65. PressThe Detroit News

    NAC votes 8-1 for the RenCen community benefits package

    The Neighborhood Advisory Council (NAC) voted 8-1 on Tuesday, October 27, in the evening to recommend that City Council approve a $133.3 million community benefits package for the $2.2 billion RenCen project. It includes $43.5 million in direct developer spending, nearly $90 million in PILOT payments to the city, $10 million for housing and 20% of 934 units as affordable. Teron Haynes Jr. cast the only no vote; the agreement goes to the council's Planning and Economic Development Committee on November 12.

  66. PressDetroit Free Press

    Do Bedrock and GM give enough in the RenCen community benefits deal?

    The Neighborhood Advisory Council (NAC) gave preliminary approval on Tuesday, October 27, to a community benefits package for the $2.2 billion RenCen redevelopment, negotiated with Bedrock and GM. The deal followed weeks of talks and more than 500 public comments since August. Some people question whether it is enough, and more votes lie ahead.

  67. PressYahoo

    Heated RenCen clash: Bedrock CEO calls councilman's questions 'indecent'

    At the City Council planning and economic development committee on Thursday, October 22, Bedrock CEO Jared Fleisher called Councilman Denzel McCampbell's position indecent three times. McCampbell had asked why part of the property won't become city-owned and said Detroiters still don't see the real benefit of the $2.2 billion plan. He answered that it's indecent to respond that way to questions; the full City Council still has to give final approval.

    Also reported by: The Detroit News, Belleville News-Democrat

  68. PressClickOnDetroit | WDIV Local 4

    8-1: NAC backs $133.3 million community benefits package for the RenCen

    The Neighborhood Advisory Council (NAC) voted 8-1 on Tuesday evening, October 27, to recommend the community benefits package for the $2.2 billion RenCen redevelopment. The $133.3 million package includes $43.5 million in direct developer spending plus nearly $90 million in PILOT payments to the city. Teron Haynes Jr. voted no because the plan has no public ownership or revenue-sharing; it goes to City Council's Planning and Economic Development Committee on November 12, with a full council vote later.

  69. PressClickOnDetroit | WDIV Local 4

    NAC votes 8-1 for $133.3 million benefits package on RenCen project

    The Neighborhood Advisory Council (NAC) voted 8-1 on Tuesday evening, October 27, to recommend a $133.3 million community benefits package to City Council for the $2.2 billion RenCen and east riverfront redevelopment. It includes $43.5 million in direct developer spending and nearly $90 million in voluntary PILOT payments. Bedrock CEO Jared Fleisher says all surplus proceeds after bills go to civic causes, while critics wanted public ownership or revenue-sharing. Detroit City Council makes the final call.

    Also reported by: ClickOnDetroit | WDIV Local 4, WDIV Local 4

  70. PressBelleville News-Democrat

    Bedrock CEO calls councilman's RenCen deal questions 'indecent'

    The Bedrock CEO called a city councilman's questions about the Detroit Renaissance Center deal "indecent," The Belleville News-Democrat reports.

    Also reported by: The Detroit News

  71. Presswww.inc.com

    Gilbert pledges $1 billion to a new nonprofit to own the RenCen

    Dan Gilbert, Bedrock's founder, pledged about $1 billion on Monday, October 19, to a new nonprofit that would develop, own and operate the RenCen and the 35-acre east riverfront. The money would never be repaid, and neither Gilbert nor his companies would take profits. Bedrock would manage the project at no cost, and Detroit City Council has the final say.

  72. PressDetroit Free Press

    What happened to Detroit's earlier 'Transformational' projects before the RenCen?

    None of Detroit's three earlier Transformational Brownfield developments is fully finished: three of four parts of Bedrock's first project are done or nearly done, District Detroit has started only one of 10 projects (Founders Hall), and Future of Health has one of six under construction. The $2.2 billion Bedrock-GM RenCen plan would be the fourth since 2017, and the two want approval before year's end because they fear the next governor, taking office in January, could change the process. The RenCen request would capture up to $300 million in state taxes from 2032 to 2051.

    Also reported by: Yahoo

  73. PressBridgeDetroit

    “Indecent”: Bedrock’s CEO answers a council member’s RenCen questions

    Bedrock CEO Jared Fleisher called Council Member Denzel McCampbell’s position “indecent” three times at the City Council’s Planning and Economic Development Committee hearing on Thursday, October 22. McCampbell had asked why the roughly $2.2 billion RenCen plan needs public money and why part of the site won’t become city-owned. Fleisher said the project returns 1% with the incentives and loses money without them; the developers are seeking about $548 million in tax breaks and subsidies over 30 years.

    Also reported by: BridgeDetroit

  74. PressCrain's Detroit

    Gilbert pledges $1B to a nonprofit to remake the RenCen and east riverfront

    Dan Gilbert, Bedrock's founder, pledged about $1 billion to a new nonprofit that would redevelop, own and operate the RenCen and the 35-acre east riverfront. Bedrock CEO Jared Fleisher announced it Monday, October 19, saying the gift will never be repaid and Bedrock manages the project at no cost. The plan includes affordable housing, space for small businesses and 18 acres of public space; Detroit City Council still has the final say on incentives and benefits.

    Also reported by: DJC, Crain's Detroit, Deadline Detroit, RAW Detroit, FOX 2 Detroit

  75. PressCity Bureau Documenters

    What did the NAC ask of the RenCen developers? Notes from CBO meeting #6 are up

    The Neighborhood Advisory Council (NAC) presented its recommended impacts and benefits for the RenCen and east riverfront project on Tuesday, October 6, at 6 p.m. at the Coleman A. Young Municipal Center. The recommendations focus on connection, place, opportunity and experience, with new chances for young people to enjoy public spaces by the riverwalk. The Detroit News reports about 90 requests totaling $45 million, and the developers' response is the next step in the Community Benefits process.

    Also reported by: City Bureau Documenters

  76. PressWDIV Local 4

    Dan Gilbert pledges $1 billion to redevelop the RenCen and east riverfront

    Dan Gilbert, founder of Bedrock and Rocket Companies, pledged about $1 billion at a press conference on Monday, October 19, to create a new nonprofit that will redevelop, own and operate the Renaissance Center and the east riverfront. Bedrock CEO Jared Fleisher said the group will not be driven by a commercial motive. Any surplus after the project pays its bills must be reinvested in the community, and GM is also putting money in.

    Also reported by: Billionaires.Africa, Enidnews.com, Finance & Commerce, REBusinessOnline, ClickOnDetroit | WDIV Local 4

  77. PressThe Detroit News

    Dan Gilbert pledges $1 billion for the RenCen revamp

    Bedrock chairman Dan Gilbert pledged $1 billion to redevelop the Renaissance Center and is creating a new 501(c)(4) nonprofit to manage it. Total project cost could reach $2.2 billion, including GM investments. The Detroit Downtown Development Authority has put in $75 million, which will be reimbursed, and the project is seeking more than $300 million in other tax benefits.

    Also reported by: myMotherLode.com, Times Union, CT Insider, The Seattle Times, Toronto Star

  78. PressBridgeDetroit

    What's next for the RenCen? Dan Gilbert pledges $1 billion to redevelop it

    Dan Gilbert announced a $1 billion pledge on Monday, October 19, for a nonprofit to redevelop, own and operate the Renaissance Center and the 35-acre east riverfront district. Total cost may reach $2.2 billion, Towers 300 and 400 would be demolished, and the hotel would shrink from 1,300 to 858 rooms. Detroit City Council still has to approve the plan, and the NAC's community benefits process is still under way.

  79. PressFacebook

    Could the RenCen agreement be final the week of October 26?

    The agreement between Bedrock, GM and a community group could be final as soon as the week of October 26, the Detroit Free Press wrote on Wednesday, October 21. Two days earlier, on Monday, October 19, Dan Gilbert pledged $1 billion to a new nonprofit that would develop, own and operate the RenCen and the east riverfront.

  80. PressTHIRTEEN - New York Public Media

    How is the Detroit Renaissance Center being redeveloped?

    The redevelopment of the Detroit Renaissance Center is the subject of a segment, THIRTEEN - New York Public Media reports.

  81. PressTHIRTEEN - New York Public Media

    Bedrock CEO talks RenCen redevelopment plans on American Black Journal

    Bedrock CEO Jared Fleisher shares details on the plans to redevelop the Renaissance Center in Season 54, Episode 42 of American Black Journal. The same episode covers October as National Book Month and "Destination Detroit," and THIRTEEN carries the show.

  82. PressBelleville News-Democrat

    RenCen nonprofit plan draws questions and skepticism at community benefits meeting

    The Neighborhood Advisory Council (NAC) pressed Bedrock and GM for stronger community commitments on the $2 billion RenCen redevelopment at its meeting at the Coleman A. Young Municipal Center on Tuesday, October 20, in the evening. Some residents questioned the newly announced nonprofit that would redevelop, own and operate the RenCen and the 35-acre east riverfront, and some called for public ownership. Bedrock's Jake Chidester said it is "not revenue sharing" but 100% of proceeds going to community benefit; the weekly talks continue.

  83. PressThe Detroit News

    RenCen nonprofit draws questions at Community Benefits meeting

    The Neighborhood Advisory Council (NAC) did not finish talks with Bedrock and GM at its Tuesday, October 20, evening meeting at the Coleman A. Young Municipal Center, so no vote happened. A resident asked why the nonprofit funded by Dan Gilbert's $1 billion pledge is a 501(c)(4), not a 501(c)(3). Bedrock's Jake Chidester said the money is a gift that won't be repaid. NAC Chair Jamaine Dickens said a vote may be possible at the next public meeting on Tuesday, October 27, and City Council must give final approval.

  84. PressDetroit Free Press

    RenCen community benefits deal isn't done, but parking offer is moving closer

    The Neighborhood Advisory Council (NAC) did not finalize the RenCen redevelopment's Community Benefits agreement at its Tuesday, October 20, meeting, though it had been expected to. Bedrock now offers Detroiters the first 90 minutes of parking free, after earlier offers of 30 and 50 percent off. The NAC may vote on a finalized deal on October 27, but its vote is only a recommendation; Detroit City Council gives final approval.

    Also reported by: Yahoo

  85. PressFOX 2 Detroit

    Nonprofit or true public ownership? Residents question Gilbert's $1 billion RenCen pledge

    At the Neighborhood Advisory Council's tenth community benefits meeting on Tuesday evening, October 20, Detroiters questioned Dan Gilbert's $1 billion pledge, announced the day before. It would fund a new nonprofit to own and run the RenCen and the east riverfront. Some residents want true public ownership, and Eden Bloom asked why Bedrock picked a 501(c)(4) over a 501(c)(3). Bedrock's Jake Chidester said the announcement legally binds the company to make no profit.

    Also reported by: FOX 2 Detroit, Yahoo

  86. PressFOX 2 Detroit

    Residents press for true public ownership of the RenCen redevelopment

    At its weekly community benefits meeting on Tuesday, October 20, in the evening, the NAC pushed Bedrock and GM for firmer commitments on affordable housing, skilled-trades jobs and protection from displacement. Several residents asked for true public ownership instead of a nonprofit, while the NAC and Bedrock edge closer on several million dollars in funds. No vote was taken; a finished agreement could go to the NAC on October 27, and City Council gives final approval.

  87. PressFOX 2 Detroit

    RenCen: what does Gilbert's $1 billion fund mean? Residents press for answers

    Detroit residents and the Neighborhood Advisory Council (NAC) met Tuesday evening, October 20, for the NAC's tenth meeting, asking how Dan Gilbert's $1 billion fund would work. It would set up a nonprofit board to own and run the RenCen and the rebuilt riverfront. Bedrock's Jake Chidester said it legally binds the company not to profit, with revenue going first to operations, debt, reserves and reinvestment.

  88. PressThe Michigan Chronicle

    Gilbert pledges $1B for a nonprofit to redevelop the RenCen and east riverfront

    Dan Gilbert, founder and chairman of Bedrock, pledged about $1 billion in development capital on Monday, October 19. A new nonprofit would redevelop, own and operate the RenCen and a 35-acre east riverfront district. Gilbert and his companies would take no profit: revenue would cover operations, debt and reserves first, and any surplus would go to Detroiters. Jamaine Dickens, chair of the area's Neighborhood Advisory Council, says the project could create 8,000 local construction jobs.

  89. PressThe Michigan Chronicle

    Dan Gilbert pledges $1 billion for the RenCen through a new nonprofit

    Rocket Mortgage co-founder Dan Gilbert says he will put $1 billion into redeveloping the Renaissance Center and manage the money through a new nonprofit. He says that structure shows residents he is not in it for the money. Total project cost might reach $2.2 billion, including GM's investment. Jamaine Dickens, chair of the area's Neighborhood Advisory Council, says the project could generate 8,000 local construction jobs.

  90. PressLifestyles Magazine

    Gilbert pledges $1 billion to remake the RenCen and east riverfront

    Dan Gilbert, founder of Bedrock and Rocket Companies, announced at a press conference on Monday, October 19, 2026, that he is pledging about $1 billion to a new nonprofit. It will redevelop, own and operate the Renaissance Center and the surrounding 35-acre east riverfront district. Gilbert and his companies take no profits and the money won't be repaid; the plan includes 18 acres of public civic space, affordable housing and space for Detroit-based small businesses.

  91. PressAxios

    Gilbert pledges $1 billion to a new nonprofit for the RenCen

    Dan Gilbert, founder of Bedrock and Rocket Companies, pledged about $1 billion in development capital on Monday, October 19, to a new nonprofit. It will redevelop, own and operate the Renaissance Center and the surrounding 35-acre east riverfront district. The gift won't be repaid and Gilbert and his companies take no profits; revenue covers operations, debt, reserves and reinvestment first, and any surplus supports Detroiters and the community.

  92. PressCBS News

    Dan Gilbert pledges $1 billion to a new nonprofit to redevelop the RenCen

    Dan Gilbert, founder of Bedrock and Rocket Companies, pledged about $1 billion in development capital to form a nonprofit that will redevelop, own and operate the RenCen and the surrounding 35-acre east riverfront. Bedrock CEO Jared Fleisher announced it Monday, October 19; the gift is not tax-deductible, Gilbert and his companies get no profits, and it will never be repaid. The nonprofit's formation and more details will be announced later.

  93. PressThe Detroit News

    Gilbert pledges $1 billion to the nonprofit that would take over the RenCen

    Dan Gilbert, founder of Rocket Companies and Bedrock, pledged about $1 billion in development capital to a new nonprofit at a Bedrock press conference on Monday, October 19. The nonprofit would redevelop, own and operate the RenCen and the 35-acre east riverfront district as part of the $2.2 billion project. The gift won't be repaid, Gilbert and his companies take no profits, and any surplus goes to Detroiters. A vote on the community benefits agreement was expected October 27.

  94. PressFacebook

    Dan Gilbert pledges $1 billion for a nonprofit to take over the RenCen and east riverfront

    Dan Gilbert, founder of Bedrock and Rocket Companies, pledged about $1 billion in development capital on Monday, October 19, to a new nonprofit. It takes over the $2.2 billion redevelopment from Bedrock and will redevelop, own and operate the RenCen and the surrounding 35-acre east riverfront. Bedrock CEO Jared Fleisher said the money will never be repaid, and Bedrock will manage the project for free.

    Also reported by: Instagram, Facebook

  95. PressWJR-AM

    Dan Gilbert pledges $1 billion to remake the RenCen

    Dan Gilbert, founder of Bedrock and Rocket Companies, pledged $1 billion at a press event on Monday, October 19, to a new nonprofit that will own, develop and operate the RenCen and a 35-acre east riverfront district. Bedrock CEO Jared Fleisher said the money will never be repaid. The plan demolishes two RenCen towers, renovates the other three and adds riverfront attractions.

  96. PressDetroit Free Press

    Gilbert pledges $1 billion for a nonprofit to take over the RenCen

    Dan Gilbert, founder of Bedrock and Rocket Companies, announced Monday, October 19, a pledge of about $1 billion in development capital for a new nonprofit. It would redevelop, own and operate the Renaissance Center and the 35-acre east riverfront district. Gilbert takes no profits and won't be repaid; revenue covers operating costs, debt and reserves first, and any surplus goes to Detroiters. The plan includes 18 acres of civic space, affordable housing and demolishing the 300 and 400 towers, with a total cost of $2.2 billion.

    Also reported by: BridgeDetroit, Yahoo

02 / Your say

When and where can you weigh in?

The RenCen’s future is being decided right now: public meetings, hearings and the Community Benefits process. Here are the next dates in Detroit time, with registration, agendas, and the slides and recordings from earlier meetings.

No meeting is scheduled right now. As soon as the City or the DEGC posts one, it shows up here.

How to have your say

  • Write to the advisory council

    The NAC wants proposals, ideas and best practices on what the neighborhood should get in return. Their address: RenCenNAC@gmail.com.

    Deadline: September 30, 2026

    Email the NAC ↗
  • Come to a meeting, or watch on Zoom

    Meetings start at 6 p.m. (registration and refreshments from 5:30) on the 13th floor of the municipal center, with parking validated at the Ford Underground Garage (30 E. Jefferson). One sign-up covers every meeting; the City says Zoom spots may be limited, so in person is encouraged.

    Register ↗
  • Take Bedrock’s survey

    What would you like on the east riverfront: food, things to do on the water, winter fun, shops? The developer’s survey asks exactly that.

    The survey ↗
  • Drop by the community hub

    Bedrock’s East Riverfront Community Hub is at 521 Atwater Street: Wednesday to Friday 11 a.m.–6 p.m., Saturday 11 a.m.–4 p.m. The front desk validates up to two hours of free parking.

    Project site ↗
  • Get the City’s updates

    The City emails updates on the project’s Community Benefits process. We show them here, live.

    Subscribe with the City ↗
  • Need an interpreter or accommodations?

    For ASL, Spanish, Arabic or Bengali interpreters or ADA accommodations at City meetings, ask seven days ahead: 313-224-4950 (TTY 711), crio@detroitmi.gov.

    Email the City ↗
  • What comes next at City Council?

    City Council’s Planning and Economic Development committee will hold a hearing on the brownfield plan, then the full Council votes, expected around November. We’ll show the date here as soon as it’s posted.

    City Council calendar ↗
Earlier meetings: slides and recordings (26)
  1. Detroit City Council: City Council Formal Session Document ↗ Document ↗
  2. Detroit City Council: Planning and Economic Development Standing Committee Document ↗ Document ↗ Document ↗ Document ↗ Document ↗
  3. Detroit City Council: City Council Formal Session Document ↗ Document ↗
  4. Detroit City Council: Planning and Economic Development Standing Committee Document ↗ Document ↗ Document ↗ Document ↗ Document ↗
  5. Detroit City Council: City Council Formal Session Document ↗ Document ↗ Document ↗ Document ↗ Document ↗
  6. Detroit City Council: City Council Formal Session Document ↗ Document ↗ Document ↗ Document ↗ Document ↗
  7. Detroit City Council: Planning and Economic Development Standing Committee Document ↗ Document ↗ Document ↗ Document ↗ Document ↗
  8. Brownfield Authority (DBRA): RENAISSANCE CENTER AND RIVEREAST DISTRICT TRANSFORMATIONAL BROWNFIELD PLAN CITY COUNCIL PUBLIC HEARING NOTICE - OCTOBER 29, 2026 Document ↗
  9. Community Benefits meeting (NAC): Backup meeting if needed: finalizing the community benefits package Slides ↗ Recording ↗
  10. Detroit City Council: City Council Formal Session Document ↗ Document ↗ Document ↗ Document ↗ Document ↗
  11. Community Hub · session: Through young eyes: what should the riverfront be?
  12. Detroit City Council: Planning and Economic Development Standing Committee Document ↗ Document ↗ Document ↗ Document ↗ Document ↗
  13. Community Benefits meeting (NAC): More on the impacts, and the community benefits package is finalized Slides ↗ Recording ↗
  14. Detroit City Council: City Council Formal Session Document ↗ Document ↗ Document ↗ Document ↗ Document ↗
  15. Community Hub · session: What’s in the riverfront for small businesses?
  16. Community Benefits meeting (NAC): The developers respond to the neighborhood’s asks Slides ↗ Recording ↗
  17. Community Hub · session: The river as a maritime asset: what should Detroit do with the water?
  18. Community Benefits meeting (NAC): NAC working meeting Slides ↗ Recording ↗
  19. Community Hub · session: What should the riverfront public space be like?
  20. DBRA Community Advisory Committee (DBRA-CAC): Special meeting on the brownfield plan
  21. Community Benefits meeting (NAC): The NAC presents the impacts and its community-benefits wish list Slides ↗ Recording ↗
  22. Brownfield Authority (DBRA) · public hearing: Public hearing on the RenCen and Rivereast District brownfield plan Document ↗
  23. Community Benefits meeting (NAC): Working meeting: what are the impacts, and what should the neighborhood ask for? Slides ↗ Recording ↗
  24. Community Benefits meeting (NAC): The NAC’s first meeting: project details and the incentives requested Slides ↗ Recording ↗
  25. Community Benefits meeting (NAC): Project introduction, and residents elect two members of the Neighborhood Advisory Council (NAC) Slides ↗ Recording ↗
  26. Community Benefits meeting (NAC): Introducing the project and the Community Benefits process Slides ↗ Recording ↗

03 / Project tracker

Where does the project stand?

From the announcement through demolition to the finished park. Every step carries its date and source, and nothing is marked done until it has actually been approved.

  1. Done

    April 15, 2024

    GM says it’s leaving

    GM moves its global headquarters to Bedrock’s Hudson’s Detroit on an initial 15-year lease, and sets out to decide the RenCen’s future with Bedrock, the City and Wayne County.10

  2. Done

    November 24, 2024

    The “right-size” concept

    Bedrock and GM propose removing the podium and the two office towers nearest the river, turning the other three into hotel, housing and office space, with a promenade along the water.1112

  3. Done

    March 4, 2025

    No historic-district study

    City Council votes 8-1 against a historic-district study, even though staff found the RenCen eligible.1314

  4. Done

    November 12, 2025

    The DDA commits up to $75 million

    The Downtown Development Authority would pay $20 million toward podium demolition and $55 million for the Jefferson promenade, plazas and roads, from 2027 to 2033. If City Council and the Michigan Strategic Fund haven’t approved the plan by March 31, 2027, the money is void.15

  5. Done

    January 12, 2026

    GM moves to Hudson’s Detroit

    Thirty years of GM at the RenCen end: staff start work on Woodward Avenue, and the logo comes off the tallest tower that same month.1617

  6. Done

    July 21, 2026

    Lansing doubles the brownfield cap

    The governor signs Public Act 36 of 2026: the statewide Transformational Brownfield cap goes from $1.6 billion to $3.2 billion, with $300 million max for any single plan.1819

  7. Done

    August 18, 2026

    The Community Benefits process begins

    The first public meeting officially debuts the plan and its renderings. About 4,600 people live in the impact area, the City says.120

  8. Done

    September 15, 2026

    The numbers come out

    A $2.237 billion budget and $472.93 million in new public incentives on top of the $75 million DDA money already approved. About $548 million in all.2122

  9. Done

    September 18, 2026

    The 144-page brownfield plan is posted

    The Transformational Brownfield Plan sets out the phases through 2036, and says the $300 million from the state can only go to RenCen work.3

  10. Done

    September 29, 2026

    Public hearing and the NAC’s wish list

    At 5 p.m. the brownfield authority takes public comment on the plan; at 6 p.m. the advisory council presents what the neighborhood wants in return.21

  11. Done

    October 20, 2026

    The community benefits package is finalized

    On the City’s schedule, the NAC may vote on the agreement at this meeting. If needed, one more round follows on October 27.18

  12. Up next

    November 2026

    City Council: hearing and vote

    The plan expects the Renaissance Zone, the PA 210 abatement and the brownfield plan itself to reach City Council in November. The Michigan Strategic Fund comes after that.39

  13. Deadline

    March 31, 2027

    Deadline: City Council and the MSF must approve

    Without both approvals by this date, the DDA’s $75 million commitment voids itself.15

  14. Later

    April 5, 2027

    Final Four: everything stays until then

    The hotel is needed for the men’s Final Four at Ford Field. Demolition prep can only begin after the April 5 championship game.2324

  15. Later

    June 30, 2027

    Podium demolition could begin

    The DDA terms place podium demolition between June 30, 2027 and December 31, 2028. Press reports say the two towers will be taken apart piece by piece, not imploded.1525

  16. Later

    2031

    Phase 1 complete

    The target: the reworked center tower with 858 hotel rooms, 200 apartments and an observation deck, ringed by 9.4 acres of new public space.3

  17. Later

    2036

    Every phase finished

    By the end of 2036 the plan has the Tower 100 apartments, the Tower 200 upgrade and RiverEast’s last phase all done. (One station first reported 2038, later corrected.)326

04 / Time machine

Slide through the years and watch the skyline change

Seven towers, fifty years. See what went up in 1977 and 1981, what changed under GM, and which two towers the plan would take down.

100200Center400300500600

2026: GM is gone, and the developers say the office towers are less than 10% leased. The plan would take down the two towers outlined in red, 300 and 400, together with the podium.337

A simplified view from the river with heights to scale. Tower positions are schematic, not a map.

05 / The plan

What would the RenCen become?

Bedrock and GM want to remake the RenCen and the east riverfront together. Every number is marked as coming from an official document or from press reports.

The river side in May 2022: the waterfront podium and the two river-facing office towers are what the redevelopment would remove
The river side in May 2022: the waterfront podium and the two river-facing office towers are what the redevelopment would remove · Notorious4life ( talk ) ( Uploads ) · CC0
  • Towers official figure

    2 towers

    Which two towers would go?

    The two 39-story office towers nearest the river, 300 and 400, plus most of the five-story podium linking the towers, which would shrink from 1.5 million to 850,000 square feet. A year-round riverfront park would take their place.339

  • Center tower official figure

    858 + 200

    Hotel, apartments and a view from the top

    The tallest tower stays: 858 hotel rooms with conference and event space, 200 market-rate apartments, a destination restaurant on the 71st floor and a public observation deck on floors 72–73.321

  • Tower 100 official figure

    384 homes

    From offices to homes

    Tower 100 becomes about 384 apartments, 134 of them affordable at up to 80% of area median income and finished to the same standard as the market units. Planned for 2033 to 2036.321

  • Tower 200 official figure

    Stays offices

    The one office tower left

    A new lobby, facade repairs and new elevators, built out floor by floor as tenants sign. Planned for 2034 to 2036, earlier if demand shows up.321

  • Housing official figure

    934 homes

    How many homes, and how many affordable?

    A total of 934: 200 in the center tower, 384 in Tower 100 and about 350 in two new RiverEast buildings. The DEGC counts 205 affordable; the plan commits to at least 20%.2131

  • Public space official figure

    18 acres

    Parks, plazas and a marina

    Plus 9.4 acres around the RenCen, the 1.1-acre Franklin-Atwater park spine, a 4.5-acre waterfront green and a 3-acre marina. A pedestrian promenade would cross 180-foot-wide Jefferson Avenue to tie downtown to the river.321

  • RiverEast official figure

    ~30 acres

    What goes where the parking lots are?

    To the east, the roughly 30-acre RiverEast District: a marina and wharf, waterfront dining and shops, family entertainment (ideas include a cinema, a water park and indoor sports) and two apartment buildings. Exact uses depend on community input and the market.321

  • Cost official figure

    $2.237B

    What does it cost, and who pays?

    That’s $1.613 billion for the RenCen and $624.1 million for RiverEast. Funding: $1.66 billion investor equity (74%), $504.8 million debt and $75 million from the DDA. For the RenCen part, Bedrock puts in $1 billion and GM $250 million.321

  • Public money official figure

    ~$548M

    How much public money is on the table?

    That’s $300 million in state tax capture through the brownfield plan over 30 years, a $133.81 million Renaissance Zone, a $39.12 million PA 210 abatement, plus the $75 million from the DDA already approved. The DEGC says the incentives make the project feasible rather than lucrative: cash-on-cash return goes from -0.8% to 1.0%.21315

  • State money official figure

    96 + 82 + 90 + 32

    Where would the $300 million go?

    RenCen work only: $96 million for demolition, $82 million for roads, parks and plazas, $90 million for Phase 1 buildings and $32 million for Tower 100. Tower 200 and RiverEast get none of it.3

  • Jobs official figure

    8,243 + 2,754

    How many jobs?

    About 8,243 construction jobs (averaging about $62,000) and 2,754 permanent direct jobs, mostly in RiverEast entertainment, sports and retail, according to the plan.321

  • The City’s math official figure

    $301.5M

    What does the City get out of it?

    The DEGC projects a 30-year net benefit to the City of $301.5 million with the project, versus $21.3 million without it. The developer opts out of the city income-tax exemption, so the City keeps that tax.213

Why does everyone quote a different number?

Because they count different things: the RenCen alone or the east riverfront too, tax breaks only or all public money, and on which date. Here they are side by side, with sources.

  • What does it cost: $1.6 billion or $2.24 billion?

    • $1.6B RenCen only, concept stage (2024–2026)1112
    • $1.613B RenCen only, official plan figure3
    • $2.237B RenCen plus RiverEast at $624.1M213

    Since September 15 the east riverfront has been part of the total. Press rounds both.

  • Public money: $473 million or $548 million?

    • $472.93M new incentives only: brownfield plan, Renaissance Zone, PA 2102140
    • ~$548M the same, plus the $75M DDA money already approved22
    • $250M → $300M the state ask: $300M is the new per-plan cap413

    Same package: the only difference is whether the DDA money is counted.

  • How big is the park: 6, 9.4, 17 or 18 acres?

    • ~6 acres riverfront freed at the RenCen, 2024 concept42
    • 9.4 acres new public space inside the RenCen footprint3
    • 17 acres City CBO page and August decks1
    • 18 acres since September 15, marina included213

    The number grew as RiverEast and the marina were added. “A 30-acre park” is press shorthand; that’s all of RiverEast’s land.

  • How many parking spaces?

    • 3,400+ Bedrock vision page intro43
    • 3,700+ City CBO page1
    • 5,532 September 15 deck summary21

    No source explains the gap. The 5,532 may count existing public garages too, but that’s unconfirmed.

  • When is it done: 2036 or 2038?

    • 2036 the official plan’s phasing3
    • 2038 one station’s first report, later corrected26

    The 2038 was an error; the plan says the end of 2036.

  • How many floors, how many rooms?

    • 73 / 70 numbered to 73, but 7, 8 and 13 are skipped: 70 real floors4431
    • ~1,300 → 858 hotel rooms today and after3

    Some stories say 72 floors or 1,200 rooms; those are roundings.

What are people saying for and against?

For it

  • Bedrock and GM say they studied the options for over two years. The four office towers are less than 10% occupied: filling them at 2025’s leasing pace would take about 82 years, and converting every tower to housing would cost about $400 million per tower, roughly $1 million per apartment.372045
  • Support letters attached to the plan come from the Detroit Riverfront Conservancy, Downtown Detroit Partnership, Detroit Regional Chamber, Visit Detroit, Greektown Neighborhood Partnership, Jefferson East Inc., the Joe Louis Greenway Partnership and three unions.3
  • The DEGC projects a $301.5 million 30-year net benefit for the City with the project, $21.3 million without it.21

Questions and criticism

  • Preservation Detroit, Docomomo US/Michigan, the Michigan Historic Preservation Network and NOMA Detroit want to keep all five towers, citing the skyline’s meaning, embodied carbon and reuse successes like Michigan Central.4647
  • Subsidy critics: the Mackinac Center says the brownfield program underdelivered, and Americans for Prosperity-Michigan asked for rigorous scrutiny. Locally, Detroiters for Tax Justice objected to diverting revenue that pays for schools and services.484922
  • CDAD called the summer CBO schedule rushed and the impact area (about 4,600 residents) too narrow. Only 2 of the 9 NAC members were elected by residents.3950
  • As of September 29, 2026 we found no lawsuit or formal petition against the project. Preservation Detroit asks supporters to contact City Council instead.47

What residents are asking for

  • Is 80% of area median income really affordable in Detroit? Residents want deeper affordability for people earning under $40,000 and for seniors, plus an affordable-housing trust fund.822
  • Jobs: Detroiters first, union jobs and living wages, apprenticeships, openings for Black workers and businesses, and security for current RenCen workers.8
  • Independent oversight, third-party financial checks, a say in future amendments, and a guarantee of no new public money if costs rise over the ten-year build.8
  • Keep the Riverwalk open during construction, design for birds on a migration route, and monitor air, noise and water. Some want all five towers kept; others ask why not remove all five.839
  • Tell Detroit’s history on the site, including the Underground Railroad and Black history, and keep meaningful pieces of the RenCen rather than erase them.8

06 / History

How did a glass fortress become Detroit’s calling card?

From Henry Ford II’s dream through the GM years to today’s overhaul: dates, people and turning points, every one sourced.

  1. 1960s

    A flour mill and a grain silo where the towers stand

    Before the towers, this stretch of riverfront east of the Civic Center was downtown’s industrial edge: warehouses, and not a single home. Accounts from the 1970s mention a flour mill, an old Packard warehouse, an abandoned rail yard and a grain silo right where the RenCen stands now.273551

  2. July 1967

    A shrinking city looks for a big move

    The July 1967 uprising sped up an exodus of residents and businesses that was already under way. Detroit had almost 2 million people in 1950, about 1.5 million by 1970 and 1.2 million by 1980. Business leaders went looking for something big and visible to turn the tide.3529

  3. November 20, 1970

    Detroit Renaissance is born

    On November 20, 1970, the Detroit Chamber of Commerce got Henry Ford II, Max Fisher, Mayor Roman Gribbs and Governor George Romney in one room. The group took the name Detroit Renaissance, with one goal: get private money flowing downtown again after 1967. Max Fisher’s own archive lists him among the 1970 founders.275230

    Henry Ford IIMax FisherRoman Gribbs

  4. November 24, 1971

    Henry Ford II rolls out a $500 million riverfront plan

    On November 24, 1971, Henry Ford II laid the proposal before the Common Council (today’s City Council): a tall hotel plus offices and shops on the river. The Detroit News called it a $500 million riverfront plan, the biggest building venture in the city’s history. Ford publicly gave Max Fisher the credit for the idea.275330

    Henry Ford IIMax Fisher

  5. 1970s

    The city’s own planner said no

    Charles Blessing, Detroit’s chief city planner at the time, opposed the project. His worry: the complex would be cut off from the very downtown it was supposed to revive. Later critics said the same thing.54

  6. May 15, 1972

    Ford and Portman show off the model

    A photo dated May 15, 1972, shows Henry Ford II and Atlanta architect John Portman presenting a model of the complex, so Portman was on board by that spring at the latest. He had just built Atlanta’s Peachtree Center, and its cylindrical Westin Peachtree Plaza tower was the direct model for Detroit’s central tower.2827

    Henry Ford IIJohn Portman

  7. 1970s

    The first plan had 15 towers

    An early model put eight more small towers, like the later Towers 500 and 600, on both sides of the site, with terraced riverfront apartments stepping down from the podium. Planning for Hart Plaza probably helped shrink the plan. The housing phase never got built.272955

    John Portman

  8. March 22, 1973

    Who won the $5,000?

    On March 22, 1973, the naming contest had its winner: Roger Lennert, 21, who worked at Ex-Cell-O Corp., took home $5,000. His mom had actually mailed the entry, and 352 other people also suggested “Renaissance Center,” but his explanation won. There were 141,537 entries; the favorites, with 542 each, were Motor City Plaza and The Hub, and car puns like Carmelot and Carmopolis rolled in too.355655

  9. May 22, 1973

    Breaking ground to “Up, Up and Away”

    Construction officially started on May 22, 1973. Henry Ford II and Mayor Roman Gribbs gave speeches, flanked by people from the partner companies. The Cass Tech band played “Up, Up and Away,” and a group of schoolkids turned the first shovels of dirt.273557

    Henry Ford IIRoman Gribbs

  10. 1973

    About 50 companies, rivals included

    Henry Ford II talked roughly 50 other companies into investing alongside Ford, including rival automakers American Motors and Chrysler (Chrysler reportedly put in $1.5 million). Sources range from “more than 40” to 52, so the exact count is disputed. The biggest partner was Ford’s own real estate arm, Ford Motor Land Development.27585535

    Henry Ford II

  11. 1973

    How much concrete do five towers take?

    The first five towers took almost 400,000 cubic yards of concrete, 40,000 tons of structural steel and 2 million square feet of glass. About 7,000 construction workers built them. At about $350 million, it was billed as the largest privately funded real estate development in the country at the time.293534

  12. 1970s

    A union job, and one fatal fall

    Ford promised an all-union crew. The Detroit Free Press told of one worker who slipped and fell about 30 feet but landed on scaffolding. Timothy Nester wasn’t so lucky: he fell four stories while working on a skylight and died.55

  13. July 1, 1976

    First tower open, hotel still going up

    The first office tower opened on July 1, 1976, while the hotel was still under construction. The Council on Tall Buildings and Urban Habitat also lists all four 39-story office towers as finished in 1976.295960

  14. August 22, 1976

    Early doubts: only 30 percent leased

    A long Detroit Free Press feature on August 22, 1976, compared the rising mass to the monolith in “2001” and asked: would it spark a renaissance, or simply become downtown? Only 30 percent of the four towers’ 2.4 million square feet of offices was leased. J.L. Hudson’s looked at moving in but passed, and the Buhl Building’s owner called it a glass menagerie.35

  15. March 1977

    The Detroit Plaza Hotel opens and nearly doubles downtown’s rooms

    The central tower opened in March 1977 as the Detroit Plaza Hotel, run by Western International Hotels (later Westin). It added about 1,400 rooms to a downtown that had only about 1,600, nearly doubling the supply. The restaurants opened at the same time, and up top sat The Summit, a revolving restaurant.61623530

    A restaurant under yellow umbrella lamps in the central atrium, curving concrete galleries above, 1977: a photo by Budapest-born Balthazar Korab
    Balthazar Korab / Library of Congress · No known restrictions
  16. 1977

    Tallest hotel on Earth, tallest building in Michigan

    At 727 feet, the tower became the tallest hotel in the world when it opened, beating Portman’s own Westin Peachtree Plaza in Atlanta. It also became Michigan’s tallest building, ending the Penobscot Building’s 49-year run, and it still held that title in 2024.29273035

    John Portman

    A black-and-white view up the cylindrical glass towers, flags in front, from Budapest-born Balthazar Korab’s archive
    Balthazar Korab / Library of Congress · No known restrictions
  17. April 15, 1977

    Dedication day: Ford shakes hands with Florence’s communist mayor

    On April 15, 1977, Henry Ford II and Mayor Coleman Young unveiled a plaque honoring the private investors. Young’s surprise guest was Elio Gabbuggiani, communist mayor of Florence, the original Renaissance city; Cold War politics nearly blocked his trip, and his handshake with Ford became the picture of the day. That night 650 guests paid $300 a couple at a Detroit Symphony Orchestra benefit, and President Jimmy Carter wired his congratulations.27306362

    Henry Ford IIColeman Young

    The newly opened Renaissance Center in 1977, photographed by Budapest-born Balthazar Korab
    Balthazar Korab / Library of Congress · No known restrictions
  18. 1977

    In front of Balthazar Korab’s lens

    Balthazar Korab, a Budapest-born architectural photographer based in the Detroit area, shot the brand-new Phase I complex in 1977. He photographed it again from the water in December 1979, and his studio shot it in 2007. The Library of Congress bought the images along with the Korab archive in 2011.64656667

    John Portman

    The first phase in 1977, photographed by Budapest-born Balthazar Korab: the four office towers and the hotel cylinder from the riverfront
    Balthazar Korab / Library of Congress · No known restrictions
  19. July 16, 1980

    Reagan, Ford and a long night on the 69th floor

    During the Republican National Convention at nearby Joe Louis Arena, July 14–17, 1980, Ronald Reagan and his top advisers worked out of a 69th-floor suite at the Detroit Plaza Hotel. On the third night the talks about a Reagan–Gerald Ford “dream ticket” played out in the tower, and Ford came up to Reagan’s suite late that night. When the deal fell apart, Reagan picked George Bush shortly after midnight.68693070

    A mounted police officer outside the Renaissance Center on July 14, 1980, during the Republican National Convention, with the planted, stepped concrete berms along Jefferson Avenue behind
    David Wipf · CC BY 2.0
  20. 1981

    Enter the Rockefellers: two more towers

    In 1979 Ford announced it would fund Phase II together with David Rockefeller’s interests, and work began on two 21-story office towers east of the original five. They were finished in 1981, bringing the complex to seven buildings. One Detroit Historical Society article puts the end of the phase in 1982.273271303329

    Henry Ford II

    The Renaissance Center mirrored in the river, with the two shorter east towers finished in 1981 already on the right: a post-1981 photo by Budapest-born Balthazar Korab
    Balthazar Korab / Library of Congress · No known restrictions
  21. April 28, 1982

    Ford makes a sale that never closes

    On April 28, 1982, Henry Ford II announced that the hotel, the four original office towers and the podium would go to investors led by Chicago real estate man Theodore Netzky. Ford admitted the original investors were getting back less than they had put in; the price wasn’t disclosed, and Towers 500 and 600 weren’t part of the deal. By January 1983 the Netzky group still had no financing.7158

    Henry Ford II

  22. June 6, 1982

    Formula One around the towers

    The first Detroit Grand Prix, a Formula One race, ran on June 6, 1982, on a street circuit wrapped around the Renaissance Center. It was privately funded through Detroit Renaissance, whose president, Robert McCabe, sold it as a race among the skyscrapers.7273

  23. January 11, 1983

    A missed payment on a $200 million mortgage

    On January 11, 1983, the main lenders declared the complex in default on its $200 million mortgage after a missed $10 million payment, with losses already at $140 million. Six days later the city learned that $2.2 million in property taxes wouldn’t be paid either. The offices were about 95 percent full, but only 40 percent of the retail space was occupied, and the hotel averaged 60 percent.58

  24. 1986

    Singapore takes the title

    In 1986 the 226-meter Westin Stamford, designed by I.M. Pei, opened in Singapore and took the world’s-tallest-hotel title away from Detroit. The RenCen had held it for about nine years.3074

  25. July 31, 1987

    The People Mover pulls in

    The Detroit People Mover opened on July 31, 1987, with its own Renaissance Center station, the first major addition to the complex. The original station was built into the big concrete berm on the Jefferson Avenue side and decorated with George Woodman’s tile work.3627

    Coleman Young

    The People Mover near the Renaissance Center in October 1987, in the system’s first months
    artistmac · CC BY-SA 2.0
  26. May 16, 1996

    GM buys its rival’s landmark

    On Thursday, May 16, 1996, General Motors said it would buy the complex and move its world headquarters there from the Albert Kahn–designed GM Building in New Center. The seller was Highgate Hotels, a Texas firm that had just agreed to buy it from the original partnership, which included both Ford and GM. The price was never disclosed; reports put it at $72–73 million. Ford, with ten years left on its lease, became GM’s tenant.33343530

    Dennis Archer

  27. November 11, 1996

    GM’s chairman moves in on Veterans Day

    On Veterans Day 1996, GM chairman John F. “Jack” Smith Jr. and other top officers moved onto the 38th and 39th floors of Tower 100. They had turned down an early idea to put them on the 13th and 14th. The rest of the staff followed over several years as leases ran out.7533

  28. 1998

    The $500 million rebuild begins

    Renovation work started in 1998, with Chicago’s Skidmore, Owings & Merrill as architects and Turner Construction as main contractor. GM billed it as the world’s largest redevelopment project by floor area.767735

  29. 1999

    A glass ring so you stop getting lost

    To fix the maze, GM added a suspended glass walkway about 12 feet wide that loops roughly an eighth of a mile around the atrium and links the towers. Each glass panel weighs about 400 pounds. A Blue Cross blog dates it to 1999; other sources just list it as part of the renovation finished in 2004.35295678

    A glass-floored stretch of the circulation ring that links the towers, at the Tower 300 marker in 2007, with GM cars below
    Mikerussell · CC BY-SA 3.0
  30. December 15, 2001

    The Wintergarden opens the RenCen to the river

    GM staff and tenants got a sneak peek at the five-story glass atrium on December 6, 2001, and it opened to the public on December 15 with the Detroit 300 Gala, which closed out the city’s 300th-birthday year. It rises 103 feet, with a roof of about 1,400 glass panes and ten 40-foot palm trees inside. It opened the complex up to the riverfront.77793530

  31. September 2002

    The berms come down

    In September 2002 the People Mover’s original Renaissance Center station came down, along with the concrete berms around it on Jefferson Avenue. The berms held heating and cooling equipment and were the most criticized part of the design. A glass entrance pavilion and a plaza took their place.36763559

    Steam rising by the concrete berms and steps on the Jefferson Avenue side on a snowy day in 1984; GM removed the berms between 2001 and 2004
    piotr iłowiecki from POLAND · CC BY-SA 2.0
  32. November 22, 2004

    A new People Mover station over the entrance

    The rebuilt Renaissance Center station opened on November 22, 2004, above GM’s new Jefferson Avenue entrance. George Woodman designed a new tile work for it, called “Path Games.”3676

    The People Mover’s Renaissance Center station in 2007, with towers 500 and 600 and their Blue Cross Blue Shield logo behind
    Mikerussell · CC BY-SA 3.0
  33. 2004

    The makeover is done

    GM’s roughly $500 million renovation wrapped up in 2004: the Wintergarden, the glass ring, a new Jefferson entrance, the GM World showroom and a hotel makeover reported at $100 million. Detroit Free Press critic John Gallagher later wrote that only after GM bought it did the complex become what it should have been all along.293530

    The towers on a snowy winter day in 2007, with flagpoles and a white pylon in front: a photo by the Korab studio, founded by Budapest-born Balthazar Korab
    Balthazar Korab / Library of Congress · No known restrictions
  34. February 2006

    Super Bowl XL’s media hub

    When Super Bowl XL was played at Ford Field on February 5, 2006, the RenCen was the media center. The Wintergarden housed media operations, and ESPN broadcast from there.807930

    ESPN’s set in the Wintergarden during Super Bowl XL week, 2006
    Mikerussell at English Wikipedia · CC BY-SA 3.0
  35. September 16, 2008

    GM turns 100 and shows off the Volt

    On September 16, 2008, GM celebrated its 100th birthday at its RenCen headquarters and unveiled the production Chevrolet Volt there. CEO Rick Wagoner called the car a symbol of the company’s future.8130

    All seven towers from Windsor in July 2008, with the new GM logo wraps
    Mike Russell · CC BY-SA 3.0
  36. 2009

    GM almost moved to Warren

    During GM’s 2009 bankruptcy, CEO Fritz Henderson proposed moving headquarters out of the RenCen to the Technical Center in suburban Warren. According to columnist Rick Haglund, the Obama administration, which was financing the bankruptcy, shot the idea down as too damaging to Detroit.54

  37. July 29, 2010

    Blue Cross brings 3,000 workers

    On July 29, 2010, Blue Cross Blue Shield of Michigan announced it would move about 3,000 employees from Southfield into 435,245 square feet of Towers 500 and 600, in phases starting in 2011. GM, the city and Wayne County were all parties to the deal.8230

  38. September 2011

    Joe Muer Seafood comes back

    In September 2011 a revived Joe Muer Seafood opened inside the RenCen, run by Andiamo owner Joe Vicari. It brought back a Detroit name that had closed on Gratiot Avenue in 1998.8335

  39. June 30, 2015

    The Ren Cen 4 cinema goes dark

    The 680-seat Ren Cen 4 theater closed on June 30, 2015, after almost 40 years. Management said it was too small and too old to compete; some moviegoers blamed how hard it was to find.3530

  40. December 29, 2017

    John Portman dies at 93

    Architect John Portman died on December 29, 2017, at 93. His New York Times obituary singled out the RenCen as a glaring example of his inward-looking buildings, while Detroit critics admitted the towers had given downtown a jolt of space-age modernism.8435

    John Portman

  41. 2018

    For sale? GM talks to Dan Gilbert

    In fall 2018 GM talked with Dan Gilbert about selling him the complex, but the talks didn’t get far, mostly because of the cost of replacing the heating and cooling systems. GM had already canceled some planned renovations in 2017 and had tried to sell the Marriott hotel.8586

    Dan Gilbert

  42. November 2019

    The Highlands takes the 71st and 72nd floors

    In November 2019 a new restaurant opened on the 71st and 72nd floors: the Highlands. It was led by James Beard Award–winning chef Shawn McClain, in the space Coach Insignia had left.8730

  43. July 19, 2022

    Barra: we’re staying, for now

    On July 19, 2022, GM CEO Mary Barra said headquarters would stay at the RenCen, while admitting she couldn’t promise what would happen over the next 5 to 15 years. By then GM used only about one and a half of the seven buildings.88

    Mary Barra

  44. December 2022

    Half of downtown’s empty offices

    After the pandemic sent office work home, the RenCen held about 53 percent of all vacant office space in downtown Detroit’s leading towers by late 2022. Between 2018 and 2023, GM’s Detroit headcount fell by more than half as teams moved to Warren.3534

  45. December 21, 2023

    Tower 500 changes hands twice in one day

    On December 21, 2023, an affiliate of New Jersey utility PSEG sold Towers 500 and 600 to a group that included Farmington Hills–based Friedman Real Estate, reportedly for about $15 million. The same day, Tower 500 was flipped to a Florida investor for $30.4 million.353889

  46. April 15, 2024

    GM announces it’s leaving

    On April 15, 2024, GM and Bedrock announced that GM’s global headquarters would move in 2025 to the new Hudson’s Detroit development a few blocks up Woodward. GM signed an initial 15-year lease for the top office floors plus street-level showroom space. GM, Bedrock, the city and Wayne County agreed to spend about a year studying the RenCen’s future.9091929334

    Mary BarraDan Gilbert

  47. November 25, 2024

    The plan: two towers come down

    On November 25, 2024, GM and Bedrock unveiled a $1.6 billion concept: tear down Towers 300 and 400 on the river side and most of the podium, and open up about six acres of riverfront. The central tower would stay a hotel with apartments on its upper floors, and another tower would become housing. The plan leaned on public money, which drew criticism in Lansing.9430

    Dan GilbertMary Barra

    The Renaissance Center from the air on the river side, December 2016: the hotel cylinder in the middle, the Wintergarden’s green glass vault below, flanked by Tower 400 (left) and Tower 300 (right), the two slated for demolition
    CucombreLibre from New York, NY, USA · CC BY 2.0
  48. January 12, 2026

    GM’s last day at the RenCen

    On Monday, January 12, 2026, GM employees started work at the new Hudson’s Detroit headquarters, ending almost 30 years at the Renaissance Center, and GM signs started coming down that same morning. It’s GM’s fourth headquarters, back on Woodward Avenue where the company started.959630

    Mary Barra

    The GM logo at the top of the hotel cylinder, July 2025
    Crisco 1492 · CC BY-SA 4.0

Myths and facts

  • False

    Jimmy Hoffa is buried in the RenCen’s foundations.

    The whole story rests on one secondhand source: Hoffa’s former driver, Marvin Elkind, quoted in a 2011 book, said a mobster hinted at it years later. No evidence has ever turned up. And construction started in May 1973, more than two years before Hoffa vanished on July 30, 1975.979827

  • False

    RoboCop’s OCP tower is the RenCen, and the movie was shot here.

    RoboCop (1987) is set in Detroit but was shot mostly in Dallas. The OCP headquarters is Dallas City Hall, extended with optical effects, and the boardroom scenes were filmed in Dallas’s Renaissance Tower. That’s where the mix-up comes from.99100

  • False

    The RenCen was built as Ford’s world headquarters.

    Ford’s real estate arm led the investor partnership, and Ford rented one office tower for about 1,700 employees, but its headquarters stayed in Dearborn. In 1996 Ford simply became GM’s tenant.71333485

  • Partly true

    The concrete berms on Jefferson Avenue were built as riot barricades.

    The berms held the heating and cooling equipment. Critics and some people at the time saw them as fortress walls, and some believed they could seal the complex off during unrest, but no source shows that was what they were designed for.30543529

  • True

    The RenCen is so big it has its own ZIP code.

    True. The complex has its own ZIP code: 48243.562935

  • Partly true

    It’s the tallest hotel in the world.

    Only from 1977 to 1986. That year Singapore’s 226-meter Westin Stamford opened and took the title.293074

  • False

    It’s still the tallest all-hotel skyscraper in the Western Hemisphere.

    People still repeat it, but it’s out of date. New York’s Courtyard & Residence Inn at 1717 Broadway (753 feet, completed 2013) was billed as the tallest stand-alone hotel in the Western Hemisphere. Fontainebleau Las Vegas (735 feet, a hotel and casino, 2023) also tops the RenCen’s 727 feet.10110210331

  • False

    It lost the tallest-hotel title in 1980 to the Hyatt Regency Crown Center in Kansas City.

    That hotel is much shorter. The title went to Singapore in 1986.10430

  • Partly true

    The hotel tower has 73 floors.

    The top floor is numbered 73, but numbers 7, 8 and 13 are skipped, so there are 70 actual floors. That’s how the Council on Tall Buildings and Urban Habitat and SkyscraperPage count it.4431

  • Partly true

    GM paid exactly $73 million.

    The price was never officially disclosed. On the day, the Associated Press reported a $72 million asking price; $73 million is the most repeated figure, and versions from $70 million to $96 million float around. The safe way to put it: a reported $72–73 million.337529

  • Partly true

    GM spent a billion dollars renovating the RenCen.

    The documented renovation program was $500 million. Estimates of about $1 billion throw in the riverfront work and later spending.29353086

  • False

    The RenCen was built with taxpayer money.

    It was privately financed and billed as the largest privately funded real estate development in the U.S. at the time. The 2024 redevelopment plan is the first to ask for big public subsidies.295530

  • False

    The rooftop restaurant still revolves.

    The revolving restaurant stopped turning around 2002. Its successors, Coach Insignia (2004) and the Highlands (2019), stay put.105106

  • Partly true

    Ford sold the RenCen in 1982.

    A sale to a group led by Theodore Netzky was announced in April 1982, but the buyers couldn’t finance it. The original partnership kept the complex until 1996.715833

  • True

    People get lost in the RenCen.

    True. The maze reputation goes back to opening day, and critics wrote about it. GM’s glass ring was added specifically to fix wayfinding, and even in 2015 moviegoers said the cinema was hard to find.355429

The RenCen on screen

  • Promotional film with a jazz-funk 'Also Sprach Zarathustra' (1976)

    It was a movie star before it opened: a promo film shot on detailed models ran to a jazz-funk take on “Also Sprach Zarathustra,” a wink at 2001: A Space Odyssey. The half-built steel frame also shows up in a public service film about the city’s new EMS and in a convention bureau film urging people to take another look at Detroit.27

  • Skyline symbol (1977)

    A 2017 Detroit Historical Society piece ranks it with the Old English D and the Joe Louis fist as a symbol of Detroit, and its image has been on countless brochures and national sports broadcasts. Nicknames: RenCen, Ren Cen, “city within a city,” GM RenCen and, officially since July 2015, GMRENCEN. A 1976 critic called it a glass menagerie.27543530

  • 1980 Republican National Convention (1980)

    Ronald Reagan’s suite was on the 69th floor of the Detroit Plaza Hotel, and that’s where the Reagan–Ford “dream ticket” talks fell apart. The convention itself was at nearby Joe Louis Arena.6869

  • Detroit Grand Prix (Formula One) (1982)

    The first Detroit Grand Prix ran on June 6, 1982, on a street circuit wrapped around the complex. Formula One cars raced at the foot of the towers.7273

  • Action Jackson (1988)

    You can spot the RenCen in the opening minutes. It keeps coming back in the establishing shots, too.8410730

  • Collision Course (1989)

    Jay Leno and Pat Morita’s buddy-cop comedy was shot in Detroit in 1986. Both the complex’s own website and Wikipedia list the RenCen as a location.8430

  • Bird on a Wire (1990)

    A chase scene in the Mel Gibson and Goldie Hawn movie was shot inside the building. So this time you get the inside, not just the skyline.8430

  • Renaissance Man (1994)

    The movie opens with Danny DeVito driving down Jefferson Avenue to a meeting inside the complex. With that title, where else would it start?8430

  • Grosse Pointe Blank (1997)

    The towers show up in establishing shots. Most of the movie, though, was filmed in Southern California.10830

  • Out of Sight (1998)

    Clooney and Lopez’s key dinner scene is set in the revolving restaurant at the top of the hotel tower. The exteriors show up too.10510930

  • MLB All-Star Game tower wrap (2005)

    For the 2005 MLB All-Star Game, the central tower was wrapped with a giant baseball crashing into it. The label gave the distance to Comerica Park’s home plate: 4,612 feet.30

  • Super Bowl XL (2006)

    The complex was the media center for Super Bowl XL. ESPN broadcast from the Wintergarden.8079

  • Killshot (2008)

    Mickey Rourke’s crime thriller opens with him driving on Jefferson and walking into the Marriott. Locals will know exactly where he is.8430

  • Real Steel (2011)

    The RenCen lobby plays the lobby of the “Spectrum” fight arena. The arena itself is Cobo, now Huntington Place.11030

  • Need for Speed (2014)

    The complex plays a big part in the Detroit sequences. If you’re watching for the towers, you won’t wait long.11130

  • GM 'Dr. EV-il' Super Bowl LVI ad (2022)

    In GM’s 2022 Super Bowl ad, Dr. Evil and his crew seize GM’s RenCen headquarters to promote electric vehicles. As a teaser, his face showed up on the tower screens.11230

07 / Today

What can you do at the RenCen today?

The towers are still open for business: the hotel, restaurants, the Wintergarden, the RiverWalk and the People Mover station. Check each place’s own site before you go.

  • The Detroit Marriott entrance and the corridor to the guest elevators at the foot of the concrete cylinder (2024)

    Hotel · Open

    Detroit Marriott at the Renaissance Center

    The center tower is a hotel of about 1,300 rooms today, with the entrance on Level 3. It stays open through the April 2027 Final Four and into mid-2027, then closes temporarily and returns with 858 rooms.113324

  • The night view over the downtown lights from the hotel’s 70th-floor Presidential Suite, October 2008

    Dining up top · Open

    Highlands & High Bar

    On floors 71–72 since 2019, closing in May 2027. The plan keeps a 71st-floor restaurant and adds a public observation deck above it.114115116

    ⏱ Mon–Thu 5–9:30 p.m., Fri–Sat 4:30–10 p.m., closed Sun

    Official site ↗
  • Restaurant · Open

    Joe Muer Seafood

    Riverview seafood on Level 1 of Tower 400, one of the towers slated to come down. It expects to stay until June 2027 and remain downtown afterward.11711542

    ⏱ Mon–Fri 11:30 a.m.–10 p.m., Sat 4–10 p.m., Sun 3–9 p.m.

    Official site ↗
  • Restaurant · Open

    Andiamo Detroit Riverfront

    Italian restaurant on the Wintergarden level that validates up to three hours in the Beaubien Garage. The owner said it would leave around the end of 2026, but it still takes reservations.11811542

    ⏱ Mon–Thu 3–10 p.m., Fri 3–11 p.m., Sat noon–11 p.m., Sun 2–9 p.m.

    Official site ↗
  • The five-story glass hall of the Wintergarden with palms, tables and holiday garlands, December 2015

    Attraction · Open

    GM Wintergarden & Riverwalk

    The five-story glass atrium has faced the river since 2001 and opens onto GM Plaza and the Detroit Riverwalk, which draws nearly 3 million visitors a year. The Riverwalk is open daily 6 a.m.–10 p.m.119120

    Official site ↗
  • The People Mover’s Renaissance Center station from Jefferson Avenue in August 2025, with a yellow train arriving on the right

    Transit · Open

    People Mover · Renaissance Center

    The station is on Level 2 of Tower 200, rides are free, and cars come about every 8–12 minutes. See the next departures live below.121122

    ⏱ Mon–Fri 6:30 a.m.–midnight, Sat 10 a.m.–midnight, Sun 10 a.m.–10 p.m.

    Official site ↗
  • Cars from the tunnel at the Detroit port of entry inspection booths in April 2013, with the Mariners’ Church tower behind

    To Canada · Open

    Detroit–Windsor Tunnel & Tunnel Bus

    The tunnel entrance is right next to the RenCen, open 24/7. The LINQ Tunnel Bus to Windsor leaves from Tunnel Plaza by Mariners’ Church: $19 one way, cards only.123124

    Official site ↗
  • Project hub · Open

    East Riverfront Community Hub

    Bedrock’s exhibit on the plan, with feedback stations and themed evenings. Groups can request a tour, and the front desk validates two hours at the Beaubien Place Garage (238 Beaubien).125

    ⏱ Wed–Fri 11 a.m.–6 p.m., Sat 11 a.m.–4 p.m.

    Official site ↗
  • Already gone · Closed

    Free tours, food court, GM World

    The building’s free tours are suspended, the podium food court is empty (Panera closed in October 2025, Burger King in November), and GM moved its vehicle showcase to Hudson’s Detroit in January 2026.1264216

  • The glass front entrance on Jefferson Avenue, where the concrete berms once stood (2024)

    Before you go · Open

    Access and house rules

    Anyone can come in for the restaurants, remaining tenants and the hotel. Visitors 17 and under need a parent or guardian 21 or older (or an organized group). Accessible entrances at the Jefferson lobby and the Wintergarden.127128129

    Official site ↗

When’s the next People Mover at Renaissance Center station?

  1. 10:08 a.m.
  2. 10:13 a.m.
  3. 10:18 a.m.

Scheduled departures, Detroit time. The station is on Level 2 of Tower 200. The full People Mover guide →

08 / People

Who dreamed it up, and who’s reshaping it now?

09 / Videos

Watch right here, one click

News, history and the plan itself. Videos play right here on the page.

  • The City of Detroit’s own recording of the April 2024 press conference where GM announces its move to Hudson’s Detroit and says it will work with Bedrock on a plan for the Renaissance Center. City of Detroit · 24:48
  • WXYZ’s November 2024 report on the day Bedrock and GM unveiled the plan, which would tear down two of the seven towers to open up the riverfront. WXYZ-TV Detroit | Channel 7 · 3:09
  • On WDIV’s Flashpoint from November 9, 2025, incoming Bedrock CEO Jared Fleisher shows the first new renderings and pitches the riverfront as a Navy Pier-style destination. The rest of the episode moves on to other Detroit news. Click On Detroit | Local 4 | WDIV · 22:58
  • Bedrock CEO Jared Fleisher talks with FOX 2 in September 2026 about the plans, just as more construction details come out. FOX 2 Detroit · 5:54
  • WXYZ in August 2026: Bedrock and GM open a community hub where Detroiters can weigh in on the plans for the Renaissance Center and the 30 acres east of it. WXYZ-TV Detroit | Channel 7 · 2:47
  • CBS Detroit, late September 2026: Bedrock says the project should wrap up in 2036, two years earlier than the documents the station obtained had projected. CBS Detroit · 1:18
  • CTV Windsor’s late-August 2026 report on the two towers coming down next year, the changing skyline and the possible upsides of the demolition. CTV News · 2:06
  • WDIV on April 15, 2024: after 28 years at the Renaissance Center, GM moves its global headquarters to Hudson’s Detroit as the anchor tenant of Bedrock’s development. Click On Detroit | Local 4 | WDIV · 4:07
  • The Detroit Historical Society’s digitized 16 mm promo film from around 1976: construction shots, models of the complex, Henry Ford II speaking and Coleman A. Young visiting the site, all set to Deodato’s jazz-funk “Also Sprach Zarathustra”. Detroit Historical Society · 8:43
  • From the WDIV archive: four minutes of the construction site in December 1973, back when the towers were still foundations and steel. Click On Detroit | Local 4 | WDIV · 4:09
  • All Things Architecture’s twelve-minute film on Henry Ford II’s vision and John Portman’s design: how the RenCen became the symbol of a Detroit rebirth, and why it ended up magnifying the city’s problems instead. All Things Architecture · 12:13
  • General Motors’ own 40-second intro to the Renaissance Center from 2020, back when it was the company’s world headquarters. General Motors · 0:41
  • A visitor’s October 2024 walk through the Renaissance Center and the GM Wintergarden, filmed when demolition rumors were already going around. Mind of Matter · 7:13
  • Flux City’s January 2026 walk through the nearly empty complex: halls, skywalks and riverfront corridors with barely a shop open, just before the redevelopment starts. Flux City · 9:54
  • A four-minute 4K drone video from 2023: a loop around the five main towers, finished with a daring fly-through. The Gardens 121 · 4:13
  • A time-lapse of the full People Mover loop, starting from the Renaissance Center station and going clockwise. MetroElfren · 2:50

11 / Sources

How do we know?

Every fact carries a source number. Official documents come first, then the press.

What do we watch, and how often?

The tracker runs on our own server and keeps every download and every page version. When a source locks us out you’ll see it here; we’ll read those from our US server later.

SourceStatusLast checkedRenCen items
Google Newsworking10 min ago448
Google Newsworking5 min ago46
BridgeDetroitworking5 min ago12
Outlier Mediaworking5 min ago1
WDET 101.9 FMworking5 min ago1
Planet Detroitworking5 min ago0
RAW Detroitworking5 min ago2
Daily Detroiterror, retrying5 min ago1
Model Dworking5 min ago0
FOX 2 Detroitworking5 min ago11
WDIV Local 4working5 min ago9
WXYZ Channel 7working5 min ago7
CBS Detroitworking5 min ago0
GM Authorityworking5 min ago2
City Bureau Documentersworking5 min ago17
City of Detroitworking5 min ago1
Detroit City Council (eSCRIBE) Officialworking10 min ago69
City of Detroit – Community Benefits Officialworking9 min ago36
DEGC / Detroit Brownfield Redevelopment Authority Officialworking9 min ago9
DEGC / Downtown Development Authority Officialworking5 min ago0
Documenters – Planning and Development (CBO)working20 min ago0
Documenters – Brownfield Authorityworking9 min ago0
Bedrock – East Riverfront Officialworking5 min ago2
GM Renaissance Center – dining directory Officialworking170 min ago0
GM Newsroom Officiallocks us out170 min ago0
Michigan Legislature Officialreachable170 min ago0
Michigan Strategic Fund (MEDC) Officiallocks us out169 min ago0
Crain’s Detroit Businesslocks us out169 min ago0
Michigan Chroniclelocks us out169 min ago0
  1. Renaissance Center and East Riverfront Projects (Community Benefits Ordinance) City of Detroit, Planning and Development Department
  2. Renaissance Center and Rivereast District: DBRA local public hearing notice, September 29, 2026 Detroit Brownfield Redevelopment Authority (DEGC)
  3. Act 381 Combined Transformational Brownfield Plan: The Renaissance Center and Rivereast District Detroit Brownfield Redevelopment Authority / Bedrock Rivereast Developer LLC, September 18, 2026
  4. Detroit East Riverfront: project site, survey and community hub Bedrock
  5. DBRA-CAC special meeting notice (Sep 30, 2026, 5:00 pm) Detroit Brownfield Redevelopment Authority
  6. Riverfront Public Space & Placemaking Session - Sep 30, 2026 Detroit Riverfront Conservancy
  7. Community Events calendar data behind the Bedrock events widget (JSON) Bedrock via eventscalendar.co
  8. CBO Meeting #4 presentation: NAC working session, 'what we have heard so far' (Sep 22, 2026) City of Detroit PDD, September 22, 2026
  9. Detroit Brownfield Redevelopment Authority (plans, notices, agendas) DEGC
  10. General Motors names Hudson's Detroit as its new global headquarters GM Newsroom, April 15, 2024
  11. Bedrock and General Motors share vision for redevelopment of Renaissance Center and Detroit Riverfront Bedrock, November 24, 2024
  12. Plan for Renaissance Center would tear down 2 towers, add housing BridgeDetroit, November 25, 2024
  13. Detroit council nixes study on making the RenCen a historic district Bridge Michigan, March 5, 2025
  14. HDAB memo: Requesting Historic Designation Eligibility for the Renaissance Center (Jan 21, 2025) City Council Historic Designation Advisory Board, January 21, 2025
  15. DDA Board regular meeting minutes, Nov 12, 2025 (RenCen support, Exhibit 1 funding terms) Downtown Development Authority (DEGC), November 12, 2025
  16. General Motors' new home in Detroit GM Newsroom, January 12, 2026
  17. As GM moves out of the Renaissance Center, businesses inside prepare for the future FOX 2 Detroit, January 12, 2026
  18. Senate Bill 723 of 2025 (Public Act 36 of 2026) - bill history Michigan Legislature
  19. House Fiscal Agency legislative analysis, SB 723 as enrolled (complete to 7-21-26) Michigan House Fiscal Agency, July 21, 2026
  20. CBO Meeting #1 presentation (Aug 18, 2026) City of Detroit PDD / Bedrock / GM, August 18, 2026
  21. CBO Meeting #3 presentation: project program + DEGC economic & fiscal analysis (Sep 15, 2026) City of Detroit PDD / Bedrock / DEGC, September 15, 2026
  22. Bedrock, GM seek $548M in subsidies for $2.2B Renaissance Center plan BridgeDetroit (with Detroit Free Press), September 16, 2026
  23. Detroit to host 2027 NCAA Men's Final Four: Here's what to know ClickOnDetroit (WDIV), April 7, 2026
  24. RenCen's Detroit Marriott Would Temporarily Close After 2027 March Madness Tournament For Demolition Crews Deadline Detroit (citing Crain's Detroit Business), December 11, 2025
  25. GM, Bedrock Moving Forward With Renaissance Center Reno GM Authority, July 23, 2026
  26. $2.24 billion Renaissance Center redevelopment project ... (story corrected: completion 2036, not 2038) WXYZ Channel 7
  27. GMRENCEN at 40 (by the Detroit Historical Society) GMRENCEN / Detroit Historical Society, April 17, 2017
  28. Henry Ford II and Architect John Portman with Model of Detroit Renaissance Center, May 1972 (object 84.1.1969.22) The Henry Ford
  29. Encyclopedia of Detroit: Renaissance Center Detroit Historical Society
  30. Renaissance Center Wikipedia
  31. Detroit Marriott at the Renaissance Center CTBUH The Skyscraper Center
  32. Renaissance Center 500 Tower CTBUH The Skyscraper Center
  33. GM buys Detroit's Renaissance Center (AP report) The Journal Record, May 17, 1996
  34. The RenCen's history: A Ford brainchild that became GM's headquarters (Nick Manes) Crain's Detroit Business, April 15, 2024
  35. Renaissance Center (GM RenCen; RenCen) Historic Detroit (Dan Austin), November 29, 2024
  36. Renaissance Center station Wikipedia
  37. CBO Meeting #2 presentation incl. NAC election results (Sep 1, 2026) City of Detroit PDD / Bedrock / GM, September 1, 2026
  38. Friedman Real Estate buys two Renaissance Center towers Crain's Detroit Business, December 2023
  39. Residents challenge timeline, vision at first Renaissance Center benefits meeting BridgeDetroit, August 19, 2026
  40. Renaissance Center redevelopment plan seeks $473M in additional tax incentives for $2.24B project WXYZ Channel 7
  41. Renaissance Center looks to future. Should taxpayers help pay the bill? Bridge Michigan, January 22, 2025
  42. A look at what's happening inside the iconic Renaissance Center as GM moves HQ The Detroit News (republished by Colliers), January 4, 2026
  43. Detroit East Riverfront - Vision Bedrock
  44. Detroit Marriott at the Renaissance Center SkyscraperPage.com
  45. Bedrock tells Detroiters its RenCen plan is 'the only path forward' BridgeDetroit, September 2, 2026
  46. Preservation Detroit is against demolition of Detroit's Renaissance Center The Architect's Newspaper, March 3, 2025
  47. Call to Action (RenCen) Preservation Detroit
  48. Michigan is debating more developer subsidies. Did the first ones work? Mackinac Center for Public Policy (James M. Hohman), September 3, 2026
  49. AFP-MI Calls for Caution on Proposed Renaissance Center Subsidies Americans for Prosperity-Michigan, June 4, 2026
  50. Detroiters weigh in on redevelopment of Renaissance Center riverfront CBS Detroit, August 19, 2026
  51. Renaissance Center opens in downtown Detroit Max M. Fisher Archives
  52. Timeline Max M. Fisher Archives
  53. "$500 million Detroit riverfront plan is unveiled by Henry Ford" (Detroit News, 1971-11-24) Max M. Fisher Archives, November 24, 1971
  54. General Motors is moving out of Renaissance Center. Now what? (Rick Haglund) Michigan Advance, April 20, 2024
  55. What does Detroit's RenCen stand for? (Malachi Barrett) BridgeDetroit, April 24, 2024
  56. 9 Random Facts About the GMRENCEN GMRENCEN (owner's site), March 2, 2016
  57. 40 years ago: Detroit Renaissance Center opens ClickOnDetroit (WDIV), April 14, 2017
  58. Glitter of Renaissance Center tarnished by default UPI Archives, January 23, 1983
  59. DDP Centennial: The Renaissance Center Downtown Detroit Partnership, August 17, 2022
  60. Renaissance Center Complex CTBUH The Skyscraper Center
  61. A Dark Age for the Renaissance Center (Elizabeth Blasius) MAS Context, January 26, 2026
  62. Renaissance Center Brought No Renaissance (Michael D. LaFaive) Mackinac Center for Public Policy, March 5, 2007
  63. The Way It Was: The History of the Renaissance Center Hour Detroit
  64. [Detroit Renaissance Center, Phase 1, Detroit, Michigan] (Balthazar Korab, 1977) Library of Congress, 1977
  65. [Detroit Renaissance Center, Detroit, Michigan. View from water] (Balthazar Korab, December 1979) Library of Congress, December 1979
  66. [Renaissance Center, Detroit, Michigan. Exterior view of skyscrapers] (Balthazar Korab Studios, 2007) Library of Congress, 2007
  67. Balthazar Korab Wikipedia
  68. How the Bush Dynasty Almost Wasn't (Richard V. Allen; reprinted from NYT Magazine, 2000-07-30) Hoover Institution, October 30, 2000
  69. 1980 Republican National Convention Wikipedia
  70. Detroit tunes up for a grand 'ol' GOP party The Christian Science Monitor, May 14, 1980
  71. Renaissance Center sold to investor group UPI Archives, April 28, 1982
  72. Detroit Renaissance Foundation president Robert McCabe said Thursday... UPI Archives, May 13, 1982
  73. 1982 Detroit Grand Prix Wikipedia
  74. Swissotel The Stamford Wikipedia
  75. GM's Jack Smith: room with a view WardsAuto, December 1, 1996
  76. New entry plaza will be the end of Renaissance Center renovation Michigan Building & Construction Trades Council newspaper, April 2, 2004
  77. GM Opens Wintergarden at the Renaissance Center for a Sneak Preview (GM release) The Auto Channel, December 7, 2001
  78. Detroit's Iconic Renaissance Center Celebrates 40 Years A Healthier Michigan (BCBSM blog), April 13, 2017
  79. GM Wintergarden GMRENCEN (owner's site)
  80. Detroit: Super Bowl XL Host CBS News, January 27, 2006
  81. Chevy Volt, inside and out CNN Money, September 16, 2008
  82. Blue Cross Blue Shield of Michigan Will Significantly Grow Its Presence in Downtown Detroit PR Newswire (BCBSM), July 29, 2010
  83. Joe Muer Seafood Returning To Detroit ClickOnDetroit (WDIV), September 26, 2011
  84. In Memoriam: John C. Portman GMRENCEN (owner's site), January 31, 2018
  85. General Motors Discussed Selling Renaissance Center As Part Of Restructuring Effort GM Authority, May 2019
  86. GM Is Leaving the Renaissance Center (Steven Cole Smith) Hagerty Media, April 16, 2024
  87. The Highlands to open atop Renaissance Center Nov. 15 under James Beard Award-winning chef The Detroit News, August 26, 2019
  88. GM Headquarters To Remain In Renaissance Center, Says Barra GM Authority, July 19, 2022
  89. Friedman bought 2 RenCen towers in December. It sold 1 later that day. Crain's Detroit Business, 2024
  90. General Motors Names Hudson's Detroit as Its New Global Headquarters Bedrock (press release), April 15, 2024
  91. General Motors names Hudson's Detroit as its new global headquarters GM Newsroom, April 15, 2024
  92. GM to move headquarters; Bedrock to help redevelop RenCen Fortune (AP), April 15, 2024
  93. GM says it will move headquarters from RenCen to Hudson's site in 2025 The Detroit News, April 15, 2024
  94. GM, Bedrock propose new vision for RenCen; call for demolition of 2 towers WDET 101.9 FM, November 25, 2024
  95. A special look inside General Motors' new global headquarters at Hudson's Detroit CBS Detroit, January 11, 2026
  96. As GM moves out of the Renaissance Center, businesses inside prepare for the future FOX 2 Detroit, January 12, 2026
  97. Hoffa's driver claims boss was buried at Renaissance ClickOnDetroit (WDIV), December 27, 2011
  98. Was Jimmy Hoffa Buried In The Foundation Of The Ren Cen? GM Authority, December 29, 2011
  99. RoboCop (1987) filming locations The Worldwide Guide to Movie Locations
  100. RoboCop Wikipedia
  101. Tallest hotel in Western hemisphere, a Marriott, tops off in NYC Skift, October 9, 2012
  102. Courtyard & Residence Inn Manhattan/Central Park CTBUH The Skyscraper Center
  103. Fontainebleau Las Vegas CTBUH The Skyscraper Center
  104. GM Renaissance Center Clio
  105. A Movie Buff's Guide to Detroit Film Locations CBS Detroit, August 26, 2014
  106. Coach Insignia, restaurant atop the Ren Cen is closing FOX 2 Detroit, January 31, 2017
  107. Action Jackson (1988) Movie Filming Locations The 80s Movies Rewind
  108. Grosse Pointe Blank filming locations The Worldwide Guide to Movie Locations
  109. Out of Sight (1998) The Motor City Flicks Project, September 29, 2013
  110. Real Steel filming locations The Worldwide Guide to Movie Locations
  111. Need for Speed (2014) - Filming & production IMDb
  112. Dr. EV-il Takes Over GM In New Super Bowl Ad: Video GM Authority, February 2022
  113. GM REN CEN - Stay GM Renaissance Center
  114. Highlands Detroit Highlands Detroit
  115. GM REN CEN - Dine directory GM Renaissance Center
  116. Highlands Detroit Restaurant on Floors 71 and 72 of RenCen Will Close in May 2027 Deadline Detroit, February 25, 2026
  117. Joe Muer Seafood (Detroit) Joe Muer Seafood
  118. Andiamo Detroit Riverfront Andiamo / Joe Vicari Restaurant Group
  119. GM Wintergarden GM Renaissance Center
  120. Detroit Riverfront Conservancy (riverfront hours) Detroit Riverfront Conservancy
  121. RC: Renaissance Center station Detroit People Mover (Detroit Transportation Corporation)
  122. Detroit People Mover schedule and service updates Detroit People Mover
  123. Detroit Windsor Tunnel Detroit Windsor Tunnel
  124. LINQ Tunnel Bus Tourism Windsor Essex Pelee Island
  125. Detroit East Riverfront - Visit Us (hub address, hours, parking validation) Bedrock
  126. GM REN CEN home (tours notice, contact) GM Renaissance Center (building management site)
  127. Sign of the times: GM brand names removed from Renaissance Center The Detroit News (syndicated via Tribune/Daily Gazette), April 6, 2026
  128. GM REN CEN - Safety / Rules of Conduct GM Renaissance Center
  129. GM REN CEN - Directions & Maps / Accessibility GM Renaissance Center

Quarter Detroit is an independent city guide. We don’t work for Bedrock, GM or the City, and nobody pays for what we write about the RenCen.

Save the plan. Share the moment.

quarterdetroit.comRenCen: the Renaissance Center’s past, present and future, liveHere’s what your friends will see
More ways to shareDiscord · Viber · Instagram · Microsoft Teams · Slack · LINE · Pinterest · Tumblr · Mastodon · Nextdoor · Flipboard · Gmail · Outlook · Yahoo Mail · With a QR code

With a QR code

Scan it with another phone, or hold it up to a friend’s camera.